Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 2/25/2020
District C
Item Creation Date: 10/17/2019

HPW – 20NJ04 PES / CP&Y, Inc.

Agenda Item#: 30.


 
                               
Summary:

**PULLED – This item will not be considered on February 26th

ORDINANCE appropriating $2,077,954.00 out of Water & Sewer System Consolidated Construction Fund; approving and authorizing a Professional Engineering Services Contract between City of Houston and CP&Y, INC for Water Main Replacement in Mandell Place, Montrose, Westmoreland and Courtland Place Subdivisions and Water Main Replacement in Midtown Area and Winlow Place, Dearbourn Place and Lancaster Place Subdivisions; providing funding for CIP Cost Recovery financed by the Water & Sewer System Consolidated Construction Fund - DISTRICT C - KAMIN

Background:

SUBJECT:  Professional Engineering Services Contract between the City and CP&Y, Inc. for Water Main Replacement in Mandell Place, Montrose, Westmoreland and Courtland Place Subdivisions and Water Main Replacement in Midtown Area and Winlow Place, Dearbourn Place, Montlew Place and Lancaster Place Subdivisions.

 

RECOMMENDATION:  An ordinance approving a Professional Engineering Services Contract with CP&Y, Inc. for Water Main Replacement in Mandell Place, Montrose, Westmoreland and Courtland Place Subdivisions and Water Main Replacement in Midtown Area and Winlow Place, Dearbourn Place, Montlew Place and Lancaster Place Subdivisions and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION:  This project is part of the City's Water Line Replacement Program and is required to replace and upgrade water lines within the City to increase circulation and availability of water.

 

DESCRIPTION/SCOPE:  The water main replacement at Mandell Place, Montrose, Westmoreland, and Courtland Place Subdivisions consists of the design of approximately 39,200 linear feet of waterline ranging from 6-inch to 12-inch diameter waterline with related appurtenances.     The water main replacement at  Midtown Area and Winlow Place, Dearborn Place, Montlew Place and Lancaster Place Subdivisions consists of the design of approximately 49,420 linear feet of waterline ranging from 6-inch to 16-inch diameter waterline with related appurtenances.

 

LOCATION:  The project area is generally bound by the following:

 

Project Name

Location

Council District

Water Main Replacement in Mandell Place, Montrose, Westmoreland and Courtland Place Subdivisions

Westheimer Rd. on the north, W Alabama St. on the south, Bagby St., Brazos St. and TX 527 Spur on the east and Dunlavy St. on the west.

C

Water Main Replacement in Midtown Area and Winlow Place, Dearborn Place, Montlew Place and Lancaster Place Subdivisions Area 1

Westheimer Rd. on the north, Richmond Ave. on the south, Dunlavy St. on the east and S. Shepherd Dr. on the west.

C

Water Main Replacement in Midtown Area and Winlow Place, Dearborn Place, Montlew Place and Lancaster Place Subdivisions Area 2

W. Gray St. on the north, Southwest Fwy. on the south, Main St. on the east and Milam St and TX 527 Spur on the west.

C

 

SCOPE OF CONTRACT AND FEE:  Under the scope of the Contract, the Consultant will perform Phase I - Preliminary Design, Phase II – Final Design, Phase III -Construction Phase Services and Additional Services.  Basic Services Fee for Phase I is based on cost of time and materials with not-to-exceed agreed upon amount.  The Basic Services fees for Phase II and Phase III will be negotiated on a lump sum amount after the completion of Phase I.  The total Basic Services appropriation is $934,054.00.

 

The Contract also includes certain Additional Services to be paid either as lump sum or on a reimbursable basis. The Additional Services include surveying, geotechnical investigation, environmental assessment, traffic control, storm water pollution prevention, and tree protection services. The total Additional Services appropriation is $954,900.00.

 

The negotiated maximum for Phase I Services is $146,353.00.

 

The total cost of this project is $2,077,954.00 to be appropriated as follows: $1,888,954.00 for Contract services and $189,000.00 for CIP Cost Recovery.

 

 

 

 

PAY OR PLAY PROGRAM:  The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATION:  The M/WBE goal for the project is set at 24%.  The Consultant has proposed the following firms to achieve this goal.

 

 

Name of Firms

Work Description

Amount

% of Total Contract

1.

Associated Testing Laboratories, Inc.

Geotechnical

$226,400.00

11.99%

2.

EJES Incorporated

Traffic Control and SWPPP

$  30,000.00

  1.59%

3.

MBCO Engineering, LLC

Surveying and Environmental Site Assessments

$541,500.00

28.67%

4.

Trigon Associates, LLC

Engineering Support

$100,000.00

  5.29%

5.

WJ International Environmental Services, Inc.

Engineering Support

$  50,000.00

  2.65%

 

 

TOTAL

$947,900.00

50.19%

 

FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

 

 

____________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS Nos. S-000035-0266-3 and S-000035-0269-3


Amount and Source of Funding:
$2,077, 954.00 - Fund No. 8500 – Water and Sewer System Consolidated Construction
Contact Information:

Juan Chavira, PE, PMP, CEM

Assistant Director, Capital Projects

Phone: (832) 395-2441

ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapsBackup Material