HPW – 20SD138 Accept Work / LEM Construction Co., Inc.

Agenda Item#: 4.


 
                               
Summary:

M2019-0563 RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $4,506,658.15 and acceptance of work on contract with LEM CONSTRUCTION CO., INC for Groundwater Facility/Re-Pump Station Improvements - Package 1 - 1.11% over the original contract amount and under the 5% contingency - DISTRICTS A - STARDIG; E - MARTIN and F - LE

Background:

SUBJECT: Accept Work for Groundwater Facility/Re-Pump Station Improvements – Package 1

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $4,506,658.15 or 1.11% over the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the City’s groundwater facility/re-pump station rehabilitation and replacement program and was required to meet the area’s water demand and also ensured compliance with the Texas Commission on Environmental Quality regulations.

 

DESCRIPTION/SCOPE: This project consisted of replacement and/or rehabilitation of booster pumps and motors, valves, piping, electrical switchgear, emergency generators, chlorine chemical feed systems and/or scrubbers and all applicable appurtenances associated with water production at the water pump station facilities for safety and reliability.  Lockwood, Andrews & Newnam, Inc. designed the project with 425 calendar days allowed for construction. The project was awarded to LEM Construction Co., Inc. with an original Contract Amount of $4,457,000.00.

 

LOCATION: The project area is located at:

 

Pump Station

Address

Council District

Bellaire Braes

12423 Bellaire Blvd.

F

Katy Addicks

11500 Old Katy Rd.

A

Kingwood A

2310 Northpark Dr.

E

Kingwood C

8750 Mills Branch Rd.

E

 

CONTRACT COMPLETION AND COST: The Contractor, LEM Construction Co., Inc., has completed the work under the subject Contract. The project was completed beyond the established completion date with an additional 204 days approved by Change Order Nos. 1, 3, 4, 9 and 10. The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order Nos. 2 - 10, is $4,506,658.15, an increase of $49,658.15 or 1.11% over the original Contract Amount and under 5% contingency amount. The increased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION: The advertised M/WBE contract goal for this project was 20.00%.  The M/WBE plan established for this project was 46.69%.  According to Office of Business Opportunity, the participation was 45.08%. Contractor’s M/WBE performance evaluation was rated Outstanding.

 

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. S-001000-0038-4

Prior Council Action:

Ordinance No. 2017-0342, dated 5-17-2017

Amount and Source of Funding:

No additional funding required.

 

Total (original) appropriation of $5,057,000.00 from Fund 8500 - Water and Sewer System Consolidated Construction Fund.

 

 

 

 

 

Contact Information:

R. Jeff Masek, P.E., CCM