Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 7/9/2019
District H
Item Creation Date: 5/28/2019

25PARK339 – Award Construction Contract – Millis Development and Construction, LLC - Squatty Lyons Park

Agenda Item#: 30.


 
                               
Summary:

O2019-531 ORDINANCE appropriating $85,000 out of Parks Special Fund; $20,057 out of Parks & Recreation Dedication Fund; $1,847,000 out of Parks Consolidated Construction Fund; awarding construction contract to MILLIS DEVELOPMENT & CONSTRUCTION, LLC for Squatty Lyons Park; setting a deadline for the bidder's execution of the contract and delivery of all bonds, insurance and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for contingencies, Civic Art Program, and engineering and materials testing services relating to construction of facilities financed by the Parks Special Fund, Parks & Recreation Dedication Fund and  Parks Consolidated Construction Fund - DISTRICT H - CISNEROS

 DELAYED BY MOTION #2019-0348

 This was Item 47 on Agenda of June 26, 2019

Background:

RECOMMENDATION: Award construction contract and appropriate funds for the project.

SPECIFIC EXPLANATION: The General Services Department (GSD) recommends that City Council award a construction contract to Millis Development and Construction, LLC on the proposal amount of $2,716,212.00 to provide construction services for Squatty Lyons Park for the Houston Parks and Recreation Department.

PROJECT LOCATION: 1701 Chamberlain (413 U)

 

PROJECT DESCRIPTION: The scope of work consists of renovating three baseball fields including replacement of fences/backstops, dugouts, field repair and regrading, irrigation and sport lighting for two of the fields. Other amenities for the park include new parking lot; a prefab building for restrooms/storage/concession; new playground; paving; fencing; site amenities; security lighting; and landscaping and irrigation.

 

The contract duration for this project is 270 calendar days from the date of the Notice to Proceed. Clark Condon Associates, Inc. is the design consultant for this project.

 

PROPOSALS: On December 14 and 21, 2018, GSD advertised a Request for Competitive Sealed Proposals (CSP) for construction services for Squatty Lyons Park. The CSP contained selection criteria that ranked respondents on experience, key personnel, safety and Hire Houston First.  The Statements of Qualifications were due on January 10, 2019, and thirteen firms responded. GSD evaluated the respondents and five of the thirteen firms received sufficient points and were requested to submit proposals. Four firms submitted proposals. Millis Development and Construction, LLC submitted the lowest proposal and offers the best value for the City based on the advertised criteria.

The four proposers are ranked as follows:

PROPOSER
1. Millis Development and Construction, LLC
2. Jerdon Enterprise, L.P.
3. The Gonzalez Group, LP
4. Times Construction, Inc.

AWARD: It is recommended that City Council award the construction contract to Millis Development and Construction, LLC, and appropriate funds for the project, including additional appropriations of $70,000.69 for engineering and materials testing services under an existing contract with ECS Southwest, LLP; and $30,033.71 for Civic Art, which represents 1.75% of the construction costs of $1,716,212, out of the Parks Consolidated Construction Fund.    

 

FUNDING SUMMARY:
$2,716,212.00     Construction Contract
$   135,810.60     5% Contingency
$     30,033.71     Civic Art (1.75% of Fund 4502)
$     70,000.69     Engineering and Materials Testing Services
$2,952,057.00     Total Funding

 

M/WBE PARTICIPATION: An 18% MBE goal and 10% WBE goal have been established for this contract. The contractor has submitted the following certified firms to achieve this goal:

FIRM (MBE):                                                       SCOPE          AMOUNT        % OF CONTRACT
Guerra Concrete Co.                                           Concrete        $156,511.00            5.76%
Texas Concrete Enterprise Ready Mix, Inc.        Concrete        $102,544.00            3.78%
C & M Construction & Utilities, Co.                      Utilities           $164,408.00            6.05%
E. Diamond Electric, Inc.                                     Electrical        $129,271.00            4.76%
                                                                                                   $552,734.00          20.35%

 

FIRM (WBE):                                                     SCOPE           AMOUNT           % OF CONTRACT
Texas Landscape Group, LLC                           Landscape      $300,710.00            11.07%

FIRM (SBE):                                                      SCOPE           AMOUNT            % OF CONTRACT
Stripes & Stops Company, Inc.                          Striping            $  6,671.00                0.25%
Wilson Electrical Contractors, Inc.                      Lighting           $23,800.00                0.88%
                                                                                                   $30,471.00                1.13%

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s “Pay or Play” Ordinance regarding health benefits for employees of City contractors. In this case, the contractor elects to play; providing health benefits to eligible employees in compliance with the City policy.

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s “Hire Houston First” (HHF) Ordinance that promotes economic opportunity for Houston businesses and supports job creation. In this case, Millis Development and Construction, LLC is a local area business company, but they were the successful awardee without application of the HHF preference.

 

CIP FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

           Capital Project Information: See attached Form A for a breakdown of capital costs.

 

WBS No: F-000705-0001-4


DIRECTOR’S SIGNATURE/DATE:

 

 

___________________________________
C. J. Messiah, Jr.
General Services Department

 

 

__________________________________
Stephen Wright
Houston Parks and Recreation Department


Amount and Source of Funding:

$     85,000.00  Parks Special Fund (4012)
$     20,057.00  Parks & Recreation Dedication Fund (4035)
$1,847,000.00  Parks Consolidated Construction Fund (4502)
$1,000,000.00 State-Grant Funded (5010) - Texas Parks & Wildlife Department 

$2,952,057.00  Total Funding 

Contact Information:

Jacquelyn L. Nisby

Council Liaison

Phone: 832-393-8023

ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
Maps Backup Material