Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 6/11/2019
District H
Item Creation Date: 4/1/2019

HPW – 20EN27 Contract Award / CSA Construction, Inc.

Agenda Item#: 32.


 
                               
Summary:

2019-445 ORDINANCE appropriating $13,875,000.00 out of Water & Sewer System Consolidated Construction Fund; awarding contract to CSA CONSTRUCTION, INC. for 69th Street Wastewater Treatment Plant Improvements (Package 6); setting a deadline for the bidder’s execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for testing services, CIP Cost Recovery and contingencies relating to construction of facilities financed by the Water & Sewer System Consolidated Construction Fund - DISTRICT H - CISNEROS

Background:
SUBJECT: Contract Award for 69th Street Wastewater Treatment Plant Improvements (Package 6).

 

RECOMMENDATION: Award a Construction Contract for 69th Street Wastewater Treatment Plant Improvements (Package 6) and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the City’s ongoing program to renew/replace inefficient components of the existing Wastewater Treatment Plant (WWTP) facilities.

 

DESCRIPTION/SCOPE: This project consists of the replacement of wastewater filtration from sand filter system to discfilter system including pumps, electrical equipment, instrumentation, concrete structure, piping, sensors and valves. The Contract duration for this project is 710 calendar days. This project was designed by Binkley & Barfield, Inc.

 

LOCATION: The project area is located at 2525 South SGT Macario Garcia Dr., Key Map Grid 494R.

 

BIDS: This project was advertised for bidding on February 1, 2019. Bids were received on February 28, 2019  The three (3) bids are as follows:

 

 

Bidder

Bid Amount

1.

CSA Construction, Inc.

$11,960,775.00

2.

PLW Waterworks, LLC

$12,112,000.00

3.

LEM Construction, Company, Inc.

$14,993,775.00

 

AWARD: It is recommended that this construction contract be awarded to CSA Construction, Inc., with a low bid of $11,960,775.00 and that Addendum Number 1 be made a part of this Contract.

 

PROJECT COST: The total cost of this project is $13,875,000.00 to be appropriated as follows:

 

· Bid Amount

$11,960,775.00

· Contingencies

$598,038.75

· Testing Services

$120,000.00

· CIP Cost Recovery

$1,196,186.25

 

Testing Services will be provided by Earth Engineering, Inc., under a previously approved contract.

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case CSA Construction, Inc., is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides benefits for some employees but will pay into the Contractor Responsibility Fund for others, in compliance with City policy.

 

M/WSBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 11.00% MBE goal and 7.00% WBE goal for this project.

 

 

MBE - Name of Firms

Work Description

Amount

% of Contract

1.

Elect-Net Services

Electrical

$875,052.00

7.32%

2.

JTR Constructors, Inc.

WWTP Equipment

$734,185.00

6.14%

3.

Rustbusters Industrial Painting, Inc.

Protective Coatings

$138,355.00

1.16%

 

 

 

TOTAL

   $1,747,592.00

14.62%

 

WBE - Name of Firms

Work Description

Amount

% of Contract

1.

BL Technology, Inc.

Equipment

$586,000.00

4.90%

 

 

TOTAL

$586,000.00

4.90%

 

SBE - Name of Firms

Work Description

Amount

% of Contract

1.

Automation Nation, Inc.

Software Engineering

$261,600.00

2.19%

 

 

TOTAL

$261,600.00

2.19%

 

 

 

 

 


FISCAL NOTE:  No significant Fiscal Operating impact is anticipated as a result of this project.

 

All known rights-of-way, easements and/or right-of-entry required for the project have been acquired.

 


_____________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS R-000509-0017-4

Amount and Source of Funding:

$13,875,000.00

Fund No. 8500

Water and Sewer System Consolidated Construction

Contact Information:

R. Jeff Masek, P.E., CCM

Assistant Director, Capital Projects

Phone: (832) 395-2387
ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapsBackup Material