Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 3/26/2019
District E, District F
Item Creation Date: 2/1/2019

HPW – 20WWO763 Hurricane Harvey Disaster Cost Recovery for Wastewater Lift Stations - Trilogy Engineering Services LLC

Agenda Item#: 71.


 
                               
Summary:

ORDINANCE approving and authorizing Professional Engineering Services Contract between the City of Houston and TRILOGY ENGINEERING SERVICES, LLC for Hurricane Harvey Disaster Cost Recovery for Wastewater Lift Stations; providing a maximum contract amount - $400,000.00 - Enterprise Fund (WBS No. R-992017-HS07-3) - DISTRICTS E - MARTIN and F - LE

TAGGED BY COUNCIL MEMBER BOYKINS

This was Item 37 on Agenda of March 20, 2019

Background:
 

SUBJECT: Professional Engineering Services Contract between the City and Trilogy Engineering Services LLC for Hurricane Harvey Disaster Cost Recovery for Wastewater Lift Stations.

 

RECOMMENDATION: (SUMMARY) An ordinance approving a Professional Engineering Services Contract with Trilogy Engineering Services LLC and allocate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the Hurricane Harvey Disaster Cost Recovery effort.  On August 25th, 2017, Hurricane Harvey inundated the City of Houston with unprecedented rainfall flooding 71 lift stations.  Due to the heavy damage caused by the storm, the City of Houston’s Wastewater Operations Branch, part of Houston Water and the Houston Public Works, requires professional engineering services to assist the branch in determining repairs/replacements/improvements needed for damaged assets, preparing insurance and FEMA claims, and substantiating those claims.  The contract duration for this project is 5 years.

 

DESCRIPTION/SCOPE: The consultant shall:

1.     Conduct a detailed site assessment to inventory all assets and determine their functionality and condition post Hurricane Harvey.

2.     Conduct a desktop analysis to determine the pre-condition of assets damaged by Hurricane Harvey and calculate the value lost due to the damage.

3.     Determine solutions for bringing assets to pre-Hurricane Harvey condition, optimal operating condition, and optimal with hardening/mitigation improvements and determine the associated costs.

4.     Prepare a technical memorandum to include all the information gathered and calculations made as well as recommendations for which solution should be implemented along with documentation to support the recommended solution.

5.     Assist Wastewater Operations in submitting Insurance and FEMA claims.

 

LOCATION:    This Project are in council districts E,F.

 

SCOPE OF CONTRACT AND FEE: Under the scope of the Contract, the Consultant will perform Single-phase Professional Engineering Services. Basic Services Fee for Single Phase is based on a lump sum with a not-to-exceed agreed upon amount.  The total Basic Services allocation is $400,000.00

 

The total cost of this project is $400,000.00 to be allocated.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, The Contractor provides benefits for some employees but will pay into the Contractor Responsibility Fund for others, in compliance with City Policy.

 

M/WBE PARTICIPATION: The M/WBE goal for the project is set at 24%. The Consultant has proposed the following firms to achieve this goal.

 

 

Name of Firms

Work Description

Amount

% of Total Contract

1.

Brian Smith Construction

 

$40,000

10.00%

2.

IMS Engineers

 

$100,000

25.00%

 

 

TOTAL

$140,000

 

35.00%

 

 

 

 

This project was presented to the Transportation Technology and Infrastructure Committee (TTI) on November 26th, 2018.

 

FISCAL NOTE: No Fiscal Note is required on grant items.

 

 

 

 

 

____________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. R-992017-HS07-3

 


Amount and Source of Funding:

$400,000.00 - Fund No. 8386 – 2015 Flood Disaster CUS



Contact Information:

Shannon Dunne

Senior Assistant Director, Wastewater Operations

Phone: (832)395-4989

 



ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet