Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 12/18/2018
District B, District C, District D, District I
Item Creation Date: 12/6/2018

25PARK331 – Accept Work – Pools/Splashpad – MacGregor, De Zavala, Lincoln, Oak Forest, and Hidalgo Parks Progressive Commercial Aquatics, Inc.

Agenda Item#: 6.


 
                               
Summary:

RECOMMENDATION from Director General Services Department for approval of final contract amount of $435,252.00 and acceptance of work on contract with PROGRESSIVE COMMERCIAL AQUATICS, INC for Pools/Splashpad - MacGregor, De Zavala, Lincoln, Oak Forest, and Hidalgo Parks - 1.37% over the original contract amount and under the 5% contingency - DISTRICTS B - DAVIS; C - COHEN; D - BOYKINS and I - GALLEGOS

Background:

RECOMMENDATION: The General Services Department recommends approval of final contract amount of $435,252.00 and acceptance of work on contract with Progressive Commercial Aquatics, Inc. for Pools/Splashpad – MacGregor, De Zavala, Lincoln, Oak Forest, and Hidalgo Parks, – 1.37% over the original contract amount and under the 5% contingency.

SPECIFIC EXPLANATION: The General Services Department recommends that City Council approve the final contract amount of $435,252.00 or 1.37% over the original contract amount, accept the work and authorize final payment to Progressive Commercial Aquatics, Inc. for construction services relating to pool and splashpad renovations at MacGregor, De Zavala, Lincoln, Oak Forest, and Hidalgo Parks, for the Houston Parks and Recreation Department.

PROJECT LOCATIONS: Park                             Address                                  Key Map      District

                                         MacGregor Park          5225 Calhoun                           534-E            D
                                         De Zavala Park           7520 Avenue J/907 76th St.     495-S             I
                                         Lincoln Park                979 Grenshaw                          412-Q            B
                                         Oak Forest Park         2100 Judiway                            452-N            C
                                         Hidalgo Park               7000 Avenue Q                         495-S             I


PROJECT DESCRIPTIONS: The scope of work consisted of the following

MacGregor Park – replaced pumps and filters; installed significant piping rework, new valves and fittings.
De Zavala Park – replaced pumps and filters; reworked selective piping and installed new valves and fittings; and filled existing pump pit.
Lincoln Park – replaced pumps and filters; reworked selective piping, installed new valves and fittings; and filled existing pump pit.
Oak Forest Park – replaced pumps and filters; reworked selective piping, installed new valves and fittings; and filled existing pump pit.
Hidalgo Park – replaced splashpad surfacing.

CONTRACT COMPLETION AND COST: The contractor completed the project within the original contract time of 120 days. The final cost of the project including Change Order No. 1 is $435,252.00, an increase of $5,902.00 over the original contract amount.

PREVIOUS CHANGE ORDER: Change Order No. 1 added expansion joints to the existing splashpad concrete base pad and added custom color for the splashpad surfacing at Hidalgo Park.

M/W/SBE PARTICIPATION: This contract is exempt from the M/WBE subcontracting provisions because the value of the contract did not exceed the threshold of $1 million required for a goal oriented contract as provided in §15-82 of the Houston Code of Ordinances.

WBS No: F-000703-0013-4


DIRECTOR’S SIGNATURE/DATE:

 


___________________________________
C. J. Messiah, Jr.
General Services Department


__________________________________
Stephen Wright
Houston Parks and Recreation Department

Prior Council Action:
Ordinance No. 2018-0040; January 17, 2018
Amount and Source of Funding:

 

No Additional Funding Required

 

Previous Funding:

$ 450,817.50 Parks Consolidated Construction Fund (4502)

Contact Information:

 

Jacquelyn L. Nisby 

Council Liaison 

Phone: 832-393-8023

 

 

ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
Site and Vicinity MapsBackup Material