Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 12/18/2018
District A, District D, District I, District J
Item Creation Date: 12/5/2018

25PARK330 – Accept Work – Pool and Splashpad Renovations – Agnes Moffitt, Burnett Bayland, Clinton, and Yellowstone Parks Hancock Pool Services, Inc.

Agenda Item#: 5.


 
                               
Summary:

RECOMMENDATION from Director General Services Department for approval of final contract amount of $487,084.00 and acceptance of work on contract with HANCOCK POOL SERVICES, INC for Pool and Splashpad Renovations - 4.52% over the original contract amount and under the 5% contingency - DISTRICTS A - STARDIG; D - BOYKINS; I  - GALLEGOS and J - LASTER

Background:

RECOMMENDATION: The General Services Department recommends approval of final contract amount of $487,084.00 and acceptance of work on the contract with Hancock Pool Services, Inc. for Pool and Splashpad Renovations – Agnes Moffitt, Burnett Bayland, Clinton, and Yellowstone Parks – 4.52% over the original contract amount and under the 5% contingency.

SPECIFIC EXPLANATION: The General Services Department recommends that City Council approve the final contract amount of $487,084.00 or 4.52% over the original contract amount, accept the work and authorize final payment to Hancock Pool Services, Inc., for construction services relating to pool and splashpad renovations at Agnes Moffitt, Burnett Bayland, Clinton, and Yellowstone Parks for the Houston Parks and Recreation Department.

PROJECT LOCATIONS: Park                               Address                      Key Map             District
                                         Agnes Moffitt Park         10645 Hammerly           499-R                   A
                                         Burnett Bayland Park     6000 Chimney Rock     531-B                    J
                                         Clinton Park                   200 Mississippi             495-U                     I
                                         Yellowstone Park           3820 Yellowstone          533-L                    D


PROJECT DESCRIPTIONS: The scope of work consisted of the following:
Agnes Moffitt Park – replaced the pump and filter plan.
Burnett Bayland Park – demolished an underground splashpad mechanical vault and replaced it with an above-ground steel vault; replaced spray nozzles and splashpad surfacing.
Clinton Park – replaced the pump and filter plan and raised the pool mechanical pit.
Yellowstone Park – replaced the pump and filter plan and raised the pool mechanical pit.

 

CONTRACT COMPLETION AND COST: The contractor completed the project within 314 days: the original contract time of 120 days plus 194 days approved by Change Orders. The final cost of the project including Change Orders is $487,084.00, an increase of $21,084.00 over the original contract amount.

 

PREVIOUS CHANGE ORDERS: Change Order Nos. 1-3 provided credit for the cost of a splashpad coating at Burnett Bayland Park; removed and replaced surge tank fittings at Agnes Moffitt pool; repaired an existing water leak under the splashpad at Burnett Bayland Park; and added non-compensable days to the contract because construction was delayed until after the pool season ended in September. Additional delays in construction also occurred due to Hurricane Harvey, which impacted the contractor, subcontractors and suppliers.

 

M/W/SBE PARTICIPATION: This contract is exempt from the M/WBE subcontracting provisions because the value of the contract did not exceed the threshold of $1 million required for a goal oriented contract as provided in §15-82 of the Houston Code of Ordinances.

 

WBS No: F-000703-0012-4

 

DIRECTOR’S SIGNATURE/DATE:

 

 

__________________________________
C. J. Messiah, Jr.
General Services Department

 

__________________________________
Stephen Wright
Houston Parks and Recreation Department

Prior Council Action:
Ordinance No. 2017-0454; June 21, 2017
Amount and Source of Funding:

No Additional Funding Required

 

Previous Funding:

$489,300.00 Parks Consolidated Construction Fund (4502)

Contact Information:

Jacquelyn L. Nisby 

Council Liaison

Phone: 832-393-8023

 

ATTACHMENTS:
DescriptionType
Site and Vicinity MapsBackup Material