CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/30/2018
District H
Item Creation Date: 10/1/2018

HPW - 20EN14 Accept Work / Pepper-Lawson Waterworks, LLC

Agenda Item#: 4.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $14,368,623.38 and acceptance of work on contract with PEPPER-LAWSON WATERWORKS, LLC for 69th Street Wastewater Treatment Plant Improvements (Package 5) - 0.71% under the original Contract amount - DISTRICT H - CISNEROS

Background:

SUBJECT: Accept Work for 69th Street Wastewater Treatment Plant Improvements (Package 5)

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $14,368,623.38 or 0.71% under the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the City’s program to renew/replace inefficient components of the existing Wastewater Treatment Plant (WWTP) facilities.

 

DESCRIPTION/SCOPE: This project consisted of various improvements at 69th Street Wastewater Treatment Plant including electrical and instrumentation. Binkley & Barfield, Inc. designed the project with 700 calendar days allowed for construction. The project was awarded to Pepper-Lawson Waterworks, LLC. with an original Contract Amount of $14,471,975.00.

 

LOCATION: The project area is generally bound by Clinton Drive on the north, S/Sgt. Macario Garcia Drive on the south, Buffalo Bayou on the east and Avenue W. on the west. The project is located in Key Map Grid 494R.

 

CONTRACT COMPLETION AND COST: The Contractor, Pepper-Lawson Waterworks, LLC.  has completed the work under the subject Contract. The project was completed beyond the established completion date with an additional 181 days approved by Change Order Nos. 2, 3,  and 4. The final cost of the project, including overrun and under run of estimated unit price quantities and previously approved Change Order Nos. 1, 2, 3, 4, 5, 6 is $14,368,623.38, a decrease of $103,351.62 or 0.71% under the original Contract Amount. The decreased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION: The advertised M/WBE contract goal for this project was 11.00%. The M/WBE plan established for this project was 12.65%.  According to Office of Business Opportunity, the participation was 15.37%. Contractor’s M/WBE performance evaluation was rated Outstanding.

 

 

 

___________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. R-000509-0016-4

Prior Council Action:
Ordinance No. 2015-0036, dated 01-14-2015
Amount and Source of Funding:

No additional funding required.

 

Total (original) appropriation of $16,228,650.00 from Fund 8500 - Water and Sewer System Consolidated Construction Fund

Contact Information:

R. Jeff Masek, P.E., CCM

Assistant Director, Capital Projects

Phone: (832) 395-2387

 

 

 

 

 

 