SUBJECT: Additional Appropriation to Professional Engineering Services Contract between the City and IDS Engineering Group, Inc. for Arlington Heights Area Drainage Improvements (Sub-Project 1).
RECOMMENDATION: (SUMMARY) Approve an ordinance appropriating additional funds to the Professional Engineering Services Contract with IDS Engineering Group, Inc.
PROJECT NOTICE/JUSTIFICATION: This project is part of the Storm Drainage Capital Improvement Plan (CIP) and is required to address and reduce the risk of structural flooding. Improvements include modification of street conveyance and sheet flow, and provide detention as needed for mitigation.
DESCRIPTION/SCOPE: This project consists of design of storm drainage improvements, necessary concrete paving, curbs, sidewalks, driveways, and underground utilities.
LOCATION: The project area is generally bound by Edgebrook Drive on the north, Parliament on the south, Shaver Street on the east and Old Galveston on the west. The project is located in Key Map Grid 576G.
PREVIOUS HISTORY AND SCOPE:
|
RCA
|
Council
Approval
|
Ordinance
No.
|
Project
|
WBS No.
|
Task Performed
|
|
Original Contract
|
06/22/2011
|
2011-0508
|
Southpark and Southcrest
|
M-000277-0001-3
|
Phase I Services
|
|
First Additional Appropriation
|
12/12/2012
|
2012-1061
|
Southpark and Southcrest
|
M-000277-0001-3
|
Phase II Services
|
| Amendment and Second Additional Appropriation
|
06/19/2013
|
2013-0607
|
Southpark and Southcrest
(Sub-Project 1)
Arlington Heights
|
M-000277-0001-3
M-410006-0001-3
|
Phase III Services
Phase I Services
|
|
Third Additional Appropriation
|
02/19/2014
|
2014 -0131
|
Arlington Heights
(Sub-Project 1)
|
M-410006-0001-3
|
Phase I Services
|
|
Forth Additional Appropriation
|
11/05/2014
|
2014-0989
|
Arlington Heights
(Sub-Project 1)
|
M-410006-0001-3
|
Phase II Services
|
|
Fifth Additional Appropriation
|
02/11/2015
|
2015-0128
|
Southpark and Southcrest
(Su-Project 2)
Arlington Heights
(Sub-Project 1)
|
M-000277-0002-3
M-410006-0001-3
|
Phase II
Services
Phase III
Services
|
|
Sixth Additional Appropriation
|
09/30/2015
|
2015-0918
|
Southpark and Southcrest
(Sub-Project 2)
|
M-000277-0002-3
|
Phase III Services
|
|
Seventh Additional Appropriation
|
5/9/2017
|
2017-0301
|
Arlington Heights
(Sub-Project 1)
|
M-410006-0001-3
|
Replenish
Phase III Services
|
SCOPE OF THIS ADDITIONAL APPROPRIATION AND FEE: The requested additional appropriation will accomplish the following tasks for Arlington Heights (Sub-Project-1); A portion of funds previously appropriated for Phase III- Construction Phase Services were used for Phase II – Final Design Services to update project design with latest Infrastructure Design Manual – Chapter 10 requirements. This additional appropriation will cover Phase II and Phase III Basic Services Fee. $157,101.16 is budgeted for Basic Services Fee and $10,148.84 for Additional Services.
The total requested appropriation is $183,975.00 to be as follows: $167,250.00 for contract services and $16,725.00 for CIP Cost recovery.
PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.
M/WBE PARTICIPATION: The M/WBE goal established for this project is 24%. The original Contract amount and subsequent appropriations totals $2,475,563.00. The consultant has been paid $ 2,318,416.43 (93.65%) has been paid to date. Of this amount, $587,554.62 (25.34%) has been paid to M/WBE sub-consultants to date. Assuming approval of the additional appropriation the contract amount will increase to $2,642,813.00. The Consultant proposes the following plan to meet the M/WBE goal.
|
Name of Firms
|
Work Description
|
Amount
|
% Total Contract
|
|
Paid Prior MWBE
|
|
$ 587,554.62
|
22.23%
|
|
Unpaid Prior MWBE
|
|
$ 26,669.38
|
1.01%
|
|
Amani Engineering, Inc. MBE
|
Land Surveying
|
$ 37,050.00
|
1.40%
|
|
|
Total
|
$ 651,274.00
|
24.64%
|
FISCAL Note: No significant Fiscal Operating impact is anticipated as a result of this project.
___________________________________
Carol Ellinger Haddock, P.E., Director
Houston Public Works
WBS No. M-410006-0001-3