Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 11/14/2018
District A, District B, District C, District D, District F, District G, District H, District I
Item Creation Date: 9/25/2018

HPW - 20WWO741 Accept Work/Nerie Construction, LLC

Agenda Item#: 7.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $1,800,159.27 and acceptance of work on contract with NERIE CONSTRUCTION, LLC for New Front Easement Reconnections - 0.24% under the original contract amount (WW5159-02) DISTRICTS A - STARDIG; B - DAVIS; C - COHEN; D - BOYKINS; E - MARTIN; F - LE; G - TRAVIS; H - CISNEROS and I - GALLEGOS

Background:

SUBJECT: Accept Work for New Front Easement Reconnections

 

RECOMMENDATION: (Summary) Pass a motion to approve the final contract amount of $1,800,159.27, which is 0.24% under the original contract amount, accept the work, and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the Neighborhood Back Lot New Front Easement Reconnections and was required to provide the relocation of sanitary sewer services to the existing front lot main.

 

DESCRIPTION/SCOPE: This project consisted of the relocation of sanitary sewer service lines for approximately100 properties in various locations within the City of Houston. The relocations included the abandonment of the sanitary sewer services to the back lot main and the installation of new sewer services to the existing front lot main. The project was awarded to Nerie Construction, LLC with an original contract amount of $1,804,408.00. The Notice to Proceed date was 05/28/2015 and the project had 730 calendar days for completion.

LOCATION: This work order project was located at various locations within Council Districts A, B, C, D, F, G, H and I.

 

CONTRACT COMPLETION AND COST: The contractor, Nerie Construction, LLC, has completed the work under the contract. The contract was completed within the contract time. The final cost of the project is $1,800,159.27, a decrease of $4,248.73 or 0.24% under the original contract amount. Less cleaning and television inspection of sewers were needed than anticipated.        

 

MWDBE PARTICIPATION:  The MWDBE goal for this project was 24.00%.  According to the Office of Business Opportunity, the actual participation was 22.60%. The contractor was awarded an “Satisfactory” rating from the Office of Business Opportunity.

 

 

                                               

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS# R-002015-0017-4

File No. WW5159-02

 

 

 

Prior Council Action:
Ordinance No. 2015-266, dated 04/01/2015
Amount and Source of Funding:

No additional funding required.

 

 

Original appropriation of $1,909,628.00 for construction and contingencies from Water and Sewer System Consolidated Construction Fund No. 8500.

Contact Information:

Shannon Dunne

Senior Assistant Director

Phone: (832) 395-5036