SUBJECT: Accept Work for FY15 Local Drainage Project Construction Contract 1.
RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $2,039,029.98 or 1.95% over the original Contract Amount, accept Work and authorize final payment.
PROJECT NOTICE/JUSTIFICATION: This project was part of the Capital Improvement Plan (CIP) and is required to meet local storm water drainage system improvements and repairs citywide.
PREVIOUS HISTORY: The original contract was approved by October 22, 2018 by Ordinance 2014-0956. This project consisted of local storm water drainage system improvements citywide. It also addressed certain large-scale storm water drainage system repairs. The project was awarded to Reytec Construction Resources, Inc. with an Original Contract Amount of $2,000,000.00. The contract duration for this project was 730 calendar days.
LOCATION: The project areas are in various locations in Council Districts B, C, D, E, G, H & I.
Work Order No.
|
Street on the North
|
Street on the South
|
Street on the East
|
Street on the West
|
Key Map
|
Council District
|
1
|
Bretshire Drive
|
Bretshire Drive
|
Sterlingshire Street
|
Sterlingshire Street
|
455A
|
B
|
2
|
Boheme Drive
|
Hermitage Lane
|
Isolde Drive
|
Hermitage Lane
|
489L
|
G
|
3
|
Braesvalley Drive
|
Rutherglenn Drive
|
Chimney Rock Road
|
Atwell Drive
|
493K
|
H
|
4
|
Mountwood Street
|
Mountwood Street
|
Mountwood Street
|
Carleen Road
|
451H
|
C
|
5
|
De Leon Street
|
De Leon Street
|
Oak Vista Street
|
Oak Vista Street
|
493L
|
I
|
6
|
Tiel Way
|
Kirby Drive
|
S Shephard Drive
|
Tiel Way
|
492M
|
G
|
7
|
Clearway Drive
|
Clearway Drive
|
Peacock Street
|
Peacock Street
|
574E
|
D
|
8
|
Braesmont Drive
|
Braesmont Drive
|
N Braeswood Blvd
|
N Braeswood Blvd
|
531T
|
C
|
9
|
Braesmont Drive
|
Braesmont Drive
|
Beechnut Street
|
Beechnut Street
|
531P
|
C
|
10
|
Scotland Street
|
Dickson Street
|
O Reilly Street
|
O Reilly Street
|
492M
|
C
|
11
|
S Richey Street
|
S Richey Street
|
S Richey
Street
|
S Richey
Street
|
536S & W
|
E
|
12
|
Memorial Drive
|
Memorial Drive
|
Memorial Drive
|
Memorial Drive
|
489M
|
G
|
13
|
Cypress Lane
|
Palmetto Lane
|
Palmetto Lane
|
Forest Cove Drive
|
336K
|
E
|
CONTRACT COMPLETION AND COST: The Contractor, Reytec Construction Resources, Inc., has completed the work under the subject Contract. The project was completed on time with an additional 741 days approved by Change Order Nos. 2, 4 and 5. The final cost of the project, including overrun and underrun of estimated unit price is of $2,039,029.98 an increase of $39,029.98 or 1.95% over the original Contract Amount. The increase cost is a result of actual work and authorization scope. This increase is primarily the result of an overrun in various General Bid Items, which were necessary to complete the work authorizations.
M/WSBE PARTICIPATION: The advertised M/WBE contract goal for this project was 18.00%. The Award M/WBE goal for this project was 18%. The Actual goal for this project was 15.02%. According to Office of Business Opportunity, contractor’s MWSDBE Contract Compliance performance evaluation was rated unsatisfactory.
_________________________________
Carol Ellinger Haddock, P.E., Director
Houston Public Works
WBS No. M-420126-0087-4