Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/16/2018
District B, District D, District I
Item Creation Date:

20AJK13 FY16 Ditch Rehab WO#1 Accept Work - T Construction

Agenda Item#: 9.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $1,595,172.20 and acceptance of work on contract with T CONSTRUCTION LLC for FY2016 Ditch Rehab Work Order #1 - 0.30% under the original contract amount - DISTRICTS B - DAVIS; D - BOYKINS and I - GALLEGOS

Background:

SUBJECT: Accept Work for FY2016 Ditch Rehab Work Order #1.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $1,595,172.20 or 0.30% under the original Contract Amount and accept the Work.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the Houston Public Works, Storm Water Maintenance Branch program and is required to clean and inspect existing underground storm sewer system.

PREVIOUS HISTORY: The original contract was approved by City Council on September 9, 2015 by Ordinance 2015-0854. City Council also approved a first amendment along with an additional allocation of funds on March 31, 2016, Ordinance 2016-0208, the amendment approved the extension of time to allow the ongoing work orders to be completed. This project consisted of removing all debris that was obstructing the flow of storm water and inspecting and televising storm sewer lines. The Work Orders were provided on an on-call basis to rehab the City’s ditch systems. The contractor has de-silted and regraded approximately 8 miles of ditch lines in various locations throughout the City. The City of Houston designed the project with 700 calendar days allowed for construction. The project was awarded to T Construction LLC with an original Contract Amount of $800,000.00, with an additional allocation of $800,000.00 through the first amendment.

LOCATION: The project areas are in various locations in Council Districts B, D, I.

Work Order No.

Street

From

To

Key Map

Council District

 

1

Aldine Westfield

Aldine Meadows

Trenton

373V & Z;

413D, H, M, R & V

B

2

Almeda Genoa Road

SH 288

Mykawa

573P, Q, R, S & T;

574N, P, Q & R

D

 

3

Lee Road

Beltway 8

Townsan Road

374M, R & V

B

4

Almeda Genoa Road

Mykawa

Telephone

574R & 575N

D & I

 

CONTRACT COMPLETION AND COST: The Contractor, T Construction LLC, has completed the work under the subject Contract. The project was completed within the original Contract time. The final cost of the project, including overrun and underrun of estimated unit price is $1,595,172.20, a decrease of $4,827.80 or 0.30% under the original Contract Amount. The decreased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION: No City M/WBE participation goal is established for this project as the contract amount does not exceed the threshold of $1,000,000.00 required for a goal oriented contract per Section 15-82 of the Code of Ordinances.

 

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. M-430003-0001-4


Prior Council Action:

Ordinance No. 2015-854, dated 09-09-2015

Ordinance No. 2016-0208, dated 03-31-2016


Amount and Source of Funding:

No additional funding required.

(Original allocation of $800,000.00 and a subsequent allocation of $800,000.00 - Fund 2302 Stormwater).


Contact Information:

AJ Kessinger

Sr. Project Manager

Transportation & Drainage Operations

Storm Water Maintenance Branch

Phone: (832) 395-2957


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
Location MapsBackup Material