Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 10/9/2018
District A, District B, District E, District F, District G, District I, District J, District K
Item Creation Date: 7/23/2018

HPW - 20SD114 / Accept Work / Alsay Incorporated

Agenda Item#: 8.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $2,673,991.96 and acceptance of work on contract with ALSAY INCORPORATED, INC for Rehabilitation of Ground Water Wells (Package 1) - 0.42% under the original contract amount DISTRICTS A - STARDIG; B - DAVIS; E - MARTIN; F - LE; G - TRAVIS; I - GALLEGOS; J - LASTER and K - CASTEX-TATAM

Background:

SUBJECT: Accept Work for Rehabilitation of Ground Water Wells (Package 1)

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $2,673,991.96 or 0.42% under the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION:  This project was part of the City’s program to upgrade and rehabilitate ground water production facilities and was required to meet the area’s water demand and to ensure compliance with the Texas Commission on Environmental Quality regulations.

 

DESCRIPTION/SCOPE:  This project consisted of the rehabilitation of existing water wells to restore reduced pumping capacity from the wells due to wear of the pumps or plugging of the well screens. The rehabilitation efforts involved removing the pumping equipment from the wells, assessing the conditions of the wells, performing mechanical and chemical cleaning of the wells, repairing any structural damage to the wells and repair or replacement of the pumping equipment. The contract also had provisions for above ground piping and electrical repair, if needed. LBG Guyton Associates designed the project with 420 calendar days allowed for construction. The project was awarded to Alsay Incorporated with an original Contract Amount of $ 2,685,339.00.

 

LOCATION:  The project is located as follows:

 

FACILITY

ADDRESS

KEY MAP GRID

COUNCIL DISTRICT

Park Ten Well 4

14315 Park Row Blvd

488W

A

Jersey Village Well 4

7012 Mayard

408R

A

Spring Branch Well 4A

4105 Campbell

450K

A

Acres Homes Well 2A

1810 Dolly Wright

412S

B

Kingwood-3 Well 3

East End Park

298S

E

District 111 Well 2

10301 Sun City Court

528V

F

District 21 Well 1

14322 Grisby

488A

G

Southwest Well 10

4426 Southwest Frwy

491Z

G

OST Acres Well 1

4022 Banner

455Y

I

Southwest Well 4A

6002 Westpark

491I

J

Sims Bayou Well 4

12445 Hodges

570M

K

 


 

CONTRACT COMPLETION AND COST: The Contractor, Alsay Inc., has completed the work under the subject Contract. The project was completed beyond the established completion date with an additional 101 days approved by Change Order Nos. 1 and 2. The final cost of the project, including overrun and underrun of estimated unit price quantities is $2,673,991.96, a decrease of $11,347.04 or 0.42% under the original Contract Amount. The decreased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION: The advertised M/WBE contract goal for this project was 11%.  The M/WBE plan established for this project was 11%.  According to Office of Business Opportunity, the participation was 13.18%. Contractor’s M/WBE performance evaluation was rated Satisfactory.

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. S-000200-0023-3 and S-000200-0023-4

 

 

 

 

Prior Council Action:
Ordinance No. 2016-0862, dated 11-09-2016
Amount and Source of Funding:

No additional funding required.

 

Total (original) appropriation of $3,165,200.00 from Water and Sewer System Consolidated Construction Fund No. 8500

Contact Information:

R. Jeff Masek, P.E., CCM

Assistant Director, Capital Projects

Phone: (832) 395-2387

ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapsBackup Material