Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 9/5/2018
District D
Item Creation Date: 5/15/2018

20PSK26 Accept Work / JFT Construction, Inc.

Agenda Item#: 5.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $9,699,161.56 and acceptance of work on contract with JFT CONSTRUCTION, INC for Southpark and Southcrest Area Drainage and Paving Improvements (Subproject 2) - 1.14% over the original contract amount - DISTRICT D - BOYKINS

Background:

SUBJECT: Accept Work for Southpark and Southcrest Area Drainage and Paving Improvements (Subproject 2)

 

RECOMMENDATION:  (SUMMARY) Pass a motion to approve the final Contract Amount of $9,699,161.56 or 1.14% over  the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION:  This project was part of the Capital Improvement Project (CIP) and constructed storm drainage improvement to address and reduce the risk of structural flooding. Improvements included installation of a new drainage system that will provide storm water conveyance and in-line detention for mitigation.

DESCRIPTION/SCOPE:  This project consisted of the construction of storm drainage improvements, necessary concrete paving, curbs, sidewalks, driveways and underground utilities. IDS Engineering Group, Inc. designed the project with 730 calendar days allowed for construction. The project was awarded to JFT Construction, Inc. with an original Contract Amount of $9,590,243.79.

LOCATION:  The project area is generally bound by South Loop 610 on the north, Southtown Street on the south, Mykawa Road on the east and Kassarine Pass on the west.  The project is located in Key Map Grids 534 N, P, S, and T.

CONTRACT COMPLETION AND COST:  The Contractor, JFT Construction, Inc., has completed the work under the subject Contract.  The project was completed within the original contract time with an additional 25 days approved by Change Order No. 6.  The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order Nos. 1-7 is $9,699,161.56, an increase of $108,917.77 or 1.14% over the original Contract Amount and under 5% contingency amount.  The increased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION:  The advertised M/WBE contract goal for this project was 18%.  The M/WBE plan established for this project was 18%.  According to Office of Business Opportunity, the participation was 20.26%.  Contractor’s M/WBE performance evaluation was rated Outstanding.  The Contractor received a “Outstanding” rating for MWSBE participation based on their efforts.

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS Nos. M-000277-0002-4 and S-000500-0205-4

Prior Council Action:
Ordinance 2015-1009, dated October 21, 2015
Amount and Source of Funding:

No additional funding required.

 

Total (original) appropriation of $11,490,000.00: $10,319,000.00 from Fund 4042-Street and Traffic Control and Storm Drainage DDSRF and $1,171,000.00 from Fund 8500- Water & Sewer System Consolidated Construction.

 

Contact Information:

Juan Chavira, PE, PMP, CEM

Assistant Director, Capital Projects

Phone: (832) 395-2441

 

 

 

 

 

 


ATTACHMENTS:
DescriptionType
Cover SheetSigned Cover sheet
MapsBackup Material