RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $13,034,104.74 and acceptance of work on contract with HUFF & MITCHELL, INC for Sanitary Sewer Force Main Renewal and Replacement-Eppes, Frawley & Bintliff Forcemains - 1.46% over the original contract amount and under 5% contingency amount - DISTRICTS F - LE; H - CISNEROS and I - GALLEGOS

Background:

SUBJECT: Accept Work for Sanitary Sewer Force Main Renewal and Replacement - Eppes, Frawley & Bintliff Force Mains

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $13,034,104.74 or 1.46% over the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the City’s ongoing force main renewal and replacement program.

DESCRIPTION/SCOPE: This project consisted of renewal and replacement of Eppes, Frawley and Bintliff force mains. A new 30-inch gravity sewer was constructed along Frawley Street to decommission the Frawley Street lift station. A new 24-inch force main was constructed to replace the existing force main for Eppes lift station. A new 30-inch force main was constructed to replace existing force main for Bintliff lift station. CH2M Hill Engineers, Inc. designed the project with 547 calendar days allowed for construction. The project was awarded to Huff & Mitchell, Inc. with an original Contract Amount of $12,846,780.30.

LOCATION:

Project

Bound By:

Key Map Grid

Council

District

Bintliff Force Main

Along Bintliff Drive bound by Bellaire Boulevard on the north, Beechnut street on the south, Bintliff Drive to the east, and Fondren road on the west.

530H, M, L

F

Frawley Force Main

Along Frawley street bound by Fulton street on the west and Robertson street on the east.

453U, V

H

Eppes Force Main

Along Chaffin street bound by Eppes street on the south, Fairway Drive on the north, Chaffin street on the east, and Golf Crest Boulevard on the west.

534H, M

I

 

CONTRACT COMPLETION AND COST: The Contractor, Huff & Mitchell, Inc., has completed the work under the subject Contract. The project was completed beyond the established completion date with an additional 106 days approved by Change Order Nos 1, 2 and 5.  The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order Nos 2, 3, 4 and 6 is $13,034,104.74, an increase of $187,324.44 or 1.46% over the original Contract Amount and under 5% contingency amount. The increased cost is a result of the difference between planned and measured quantities.

 

M/WBE PARTICIPATION: The advertised M/WBE contract goal for this project was 20%.  The M/WBE plan established for this project was 15.70%.  According to Office of Business Opportunity, the participation was 16.25%. Contractor’s M/WBE performance evaluation was rated Satisfactory.

 

 

_________________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. R-000035-0001-4

 


Prior Council Action:

Ordinance 2014-640, dated 06-18-2014

 

 

 

 


Amount and Source of Funding:

No additional funding required.

 

Total (original) appropriation of $14,625,200.00 from Water and Sewer System Consolidated Construction

Fund No. 8500.


Contact Information:

Juan Chavira, PE, PMP, CEM

Assistant Director, Capital Projects

(832) 395-2441

 

 


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapsBackup Material