Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 5/15/2018
District C, District H, District K
Item Creation Date: 4/25/2018

25GM331 - Award Contract - UST/Stormwater Interceptors at Environmental Service Centers

Agenda Item#: 32.


 
                               
Summary:

ORDINANCE appropriating $1,955,684.64 out of the Solid Waste Consolidated Construction Fund, awarding construction contract to DNB ENTERPRISES, INC for Removal, Remediation, and Installation of Underground Storage Tanks at Environmental Service Center – South and Stormwater Interceptor Installation at Environmental Service Center – North and Northwest Service Center; setting a deadline for the bidder's execution of the contract and delivery of all bonds, insurance and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for construction of the project, material testing, project management and construction oversight, salary recovery, and contingencies relating to construction of facilities financed by the Solid Waste Consolidated Construction Fund  DISTRICTS C - COHEN; H - CISNEROS and K - VACANT

Background:

RECOMMENDATION:  Award construction contract and appropriate funds for the project.

 

 SPECIFIC EXPLANATION: The General Services Department recommends that City Council award a construction contract to DNB Enterprises, Inc., on its lowest responsive bid amount of $1,758,266.00 to provide construction services for underground storage tank removal, remediation, and installation at the Environmental Service Center (ESC) – South, and storm water interceptor installation at the ESC – North, and the Northwest Service Center for the Solid Waste Management Department.

 

PROJECT LOCATIONS:

Facility

Address

Key Map

Council District

ESC - South

11500 S. Post Oak Road

571C

K

ESC - North

5614 Neches Street

454S

H

Northwest Service Center

1245 Judiway Street

452P

C

 

PROJECT DESCRIPTION: The scope of work is as follows:

ESC – South - remove two 10,000-gallon gasoline USTs and one 10,000-gallon diesel UST, supply and install one 20,000-gallon gasoline UST and three 20,000-gallon diesel USTs, supply and install associated self-service fueling systems, remove three 4,000-gallon waste oil USTs along with associated appurtenances and install three 1,000-gallon waste oil ASTs with all appurtenances. The work also includes disposal of aqueous liquid, backfilling, compaction, waste classification, loading, hauling, and proper disposal of waste generated during site activities in accordance with all applicable federal, state and local regulations.

   ESC – North - supply and install three storm water interceptor systems.

   Northwest Service Center - supply and install one storm water interceptor system. 

   Each system is comprised of a perforated stainless-steel structure and related components.

The contract duration for this project is 180 calendar days.

 

BIDS:  The following two bids were received on January 25, 2018:

 

Bidder

Bid Amount

1

Cobb Environmental

$ 1,590,846.10* (non-responsive)

2

DNB Enterprises, Inc.

$ 1,758,266.00

 

* Bid submittal did not meet advertised M/WBE Goals as determined by the Office of Business Opportunity.

 

 AWARD: It is recommended that City Council award the construction contract to DNB Enterprises, Inc., and appropriate funds for the project, including additional appropriations of $10,000.00 for materials testing under the existing contract with Kenall, Inc., and $117,088.00 for project management and construction oversight services under the existing contract with Jaymark Engineering Corp., which includes but is not limited to soil and groundwater sampling and analytical testing.

CONSTRUCTION GOALS:    A 15% MBE goal and 13% WBE goal have been established for this contract.  The contractor has submitted the following certified subcontractors to achieve the goals:

 

FIRM (MBE)                       WORK DESCRIPTION         AMOUNT          (%) of CONTRACT

Holcomb Oil Recycling          Petroleum Recycling             $  32,879.57                   1.87

Jomar Silva Trucking             Trucking                                $  32,176.27                   1.83

Webbco Fabrication               Metal Fabrication                 $100,045.34                    5.69

C & M Construction                Storm Sewer Construction   $105,495.96                    6.00

    & Utilities                          TOTAL                                 $270,597.14                   15.39%

 

FIRM (WBE)                        WORK DESCRIPTION            AMOUNT      (%) of CONTRACT

Holes Incorporated             Concrete Cutting                  $  18,989.27                     1.08

Liberty Equipment Sales    Supplier                                 $228,574.58                   13.00

                                             TOTAL                                 $247,563.85                  14.08%

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s “Pay or Play” Ordinance regarding health benefits for employees of City contractors. In this case, the contractor has elected to pay into the Contractor Responsibility Fund in compliance with City policy.

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s “Hire Houston First” Ordinance that promotes economic opportunity for Houston businesses and supports job creation. In this case, the proposed contractor meets the requirements of Hire Houston First.

CIP FISCAL NOTE: There is no estimated impact to the operating and maintenance costs for this CIP project. Therefore, no Fiscal Note is required as stated in the Financial Policy Ordinance No. 2014-1078.

        Capital Project Information: See each attached Form A for a breakdown of capital costs.

 

WBS No. L-000080-0002-4 and L-000099-0002-4

Amount and Source of Funding:

$1,955,684.64

Solid Waste Consolidated Construction Fund (4503)

Contact Information:

Jacquelyn L. Nisby  

Phone: 832-393-8023

ATTACHMENTS:
DescriptionType
Coversheet (revised)Signed Cover sheet
MapBackup Material