20PSK17 Accept Work / Traffic Systems Construction, Inc.

Agenda Item#: 1.


 
                               
Summary:

RECOMMENDATION from Director Houston Public Works for approval of final contract amount of $2,188,912.45 and acceptance of work on contract with TRAFFIC SYSTEMS CONSTRUCTION, INC for Citywide Traffic Signal Rebuild Package #5 - 18.06% under the original contract amount - DISTRICTS A - STARDIG; B - DAVIS; C - COHEN and H - CISNEROS

Background:

SUBJECT:  Accept Work for Citywide Traffic Signal Rebuild Package #5.

 

RECOMMENDATION:  (SUMMARY) Pass a motion to approve the final Contract Amount of $2,188,912.45 or 18.06% under the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION:  This project was part of the Street & Traffic Capital Improvement Plan (CIP) and is required to meet City of Houston standards as well as to improve traffic signal, mobility, and safety at the selected intersections.

 

DESCRIPTION/SCOPE:  The project consisted of rebuilding traffic signals, curb-ramps, pavement markers, signing and other work as detailed on the plans to improve the flow of traffic and reduce accidents at these locations.  TEDSI Infrastructure Group. Inc. designed the project with 550 calendar days allowed for construction. The project was awarded to Traffic Systems Construction, Inc. with an original Contract Amount of $2,671,303.40.

 

LOCATION:  The project areas are located in various locations in Council Districts A, B, C, & H. 

Work Order

Street Intersections

Council District

Key Map

1

43rd @ Mangum

A

451L

2

Dacoma @ Mangum

A

451P & T

3

Antoine @ Long Creek

A

450G

4

Antoine @ Westview

A

531E

5

Dollywright @ West Montgomery

B

412T

6

West Montgomery @ Victory

B

412T

7

Fire Station 42@ 8675 Clinton Dr.

B

495U

8

Fire Station 84 @ 300 Block of Gears

B

372Q

9

11th @ Durham

C

452Y

10

Cavalcade @ Jensen

H

454S

 

CONTRACT COMPLETION AND COST: The Contractor, Traffic Systems Construction, Inc. has completed the work under the subject Contract. The project was completed beyond the established completion date with an additional 407 days approved by Change Order No 3. Liquidated damages in the amount of $800.00 for 1 day at $800.00/day were assessed and reflected in the final payment to the Contractor. The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order Nos. 1, 2 and 3 is $2,188,912.45, a decrease of $482,390.95 or 18.06% under the original Contract Amount and under 5% contingency amount. The decreased cost is a result of the difference between planned and measured quantities.

 

M/WSBE PARTICIPATION:  The advertised M/WBE contract goal for this project was 18%.  The M/WBE plan established for this project was 21.87%.  According to Office of Business Opportunity, the participation was 20.21%.  Contractor’s M/WBE performance evaluation was rated Satisfactory based on their good faith efforts to meet the goal.

 

 

_______________________________

Carol Ellinger Haddock, P.E., Director

Houston Public Works

 

WBS No. N-310650-0070-4

Prior Council Action:

Ordinance # 2014-0161     Dated: 02/26/2014

 

 

 

 

 

Amount and Source of Funding:

No additional funding required.

 

Total (original) appropriation $3,038,860.00 from Fund 4040 – METRO Projects Construction DDSRF

Contact Information:

Joseph T. Myers, P.E.

Acting Deputy Director, Capital Projects

Phone: (832) 395-3255


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapsBackup Material