CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 4/17/2018
District F, District J
Item Creation Date: 3/13/2018

20EN01 Additional Appropriation / IDS Engineering Group, Inc.

Agenda Item#: 24.


 
                               
Summary:

ORDINANCE appropriating $343,200.00 out of Water & Sewer System Consolidated Construction Fund as an additional appropriation to Professional Engineering Services Contract between the City of Houston and IDS ENGINEERS GROUP, INC for Lift Station Renewal and Replacement Project (as approved by Ordinance No. 2014-0385); providing funding for CIP Cost Recovery relating to construction of facilities financed by the Water & Sewer System Consolidated Construction Fund - DISTRICTS F - LE and J - LASTER

Background:

SUBJECT: Additional Appropriation to Professional Engineering Services Contract between the City and IDS Engineering Group, Inc., for Lift Station Renewal and Replacement – High Star, Alief Village, WCID #78, Roark #3, Belle Park #2, Belle Park #1 and WCID #94.  

                            

RECOMMENDATION: Approve an ordinance appropriating additional funds to the Professional Engineering Services Contract with IDS Engineering Group, Inc.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the City’s ongoing program to upgrade its wastewater lift station facilities.

 

DESCRIPTION/SCOPE: This project consists of the evaluation and design services to rehabilitate, repair, replace, and/or consolidate various lift stations and related sewer systems.

 

LOCATION:

 

Lift Station

Service

Address

Key Map Grid

Council District

1

High Star Lift Station

Replacement

12843½ High Star

528D

F

2

Alief Village Lift Station

Elimination

4237 Amir

529A

F

3

WCID #78 Lift Station

Rehabilitation

4414 Bugle

529F

F

4

Belle Park #2 Lift Station

Elimination

8003 Belle Park Drive

529K

F

5

Belle Park #1 Lift Station

Rehabilitation

7615 Belle Park Drive

529K

F

6

WCID #94 Lift Station

Replacement

7120 Imperial Point

529L

F

 

PREVIOUS HISTORY AND SCOPE: City Council approved the original Contract on April 30, 2014 under Ordinance No.2014-0385. The scope of services under the original contract consisted of Basic Services (Phase I, II and III) and various Additional Services for the preparation of one construction package which included four lift station eliminations by diversion gravity sewer and three lift station rehabilitations.

The original contract consisted of Basic Services (Phase I, II, and II) and various Additional Services.

 

Under this Contract, the Consultant completed Phase I - Preliminary Design to determine the scope of work for Phase II and III. As per the decision by the Technical Review Committee, the original scope of the project is modified to reflect the findings from Phase I – Preliminary Design which included two lift station replacements, two lift station rehabilitations and two lift station elimination by diversion gravity sewer. Additionally, the project is separated into two construction packages. Additional design funds are required to produce two separate construction packages and to account for the modified scope based on Phase I findings. The packages that were agreed to by the Technical Review Committee and noted in the Record of Decision and Action Items are the following:

 

  1. Package 1 – Replacement of two lift station and rehabilitation of two stations. One Lift station will require an upsized force main and gravity sewer system due to the additional flows provided by the COH’s Houston Water – Planning.

  2. Package 2 – Elimination by diversion gravity sewer of two lift stations.

 

Additional funds are needed to provide structural, electrical, traffic control, reprographics and geotechnical services to complete the modified scope of the project

 

SCOPE OF THIS ADDITIONAL APPROPRIATION AND FEE:  The requested additional appropriation will accomplish the following tasks: Phase II final design and Phase III Construction Phase Services for Package 1. The amount of $113,460.00 are budgeted as Basic Services Fee for Phase II and Phase III. Certain other Additional Services are also proposed to be paid as lump sum or on a reimbursable basis. The Additional Services are currently anticipated to include surveying, abstracting, geotechnical investigations, environmental site assessment, traffic control plans, independent cost estimate, preparation of designer’s O&M manual and reprographics. The total Additional Services Fee under the additional appropriation is $184,900.00

 

The total requested appropriation is $343,200.00 to be appropriated as follows: $298,360.00 for contract services and $44,840.00 for CIP Cost Recovery.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATIONThe M/WBE goal established for this project is 24%. The original Contract amount is $1,442,500.00. The Consultant has been paid $295,041.84 (20.45%) to date. Of this amount, $102,993.53 (34.91%) has been paid to M/WBE sub-consultants to date. Assuming approval of the requested additional appropriation, the contract amount will increase to $ 1,740,860.00. The Consultant proposes the following plan to meet the M/WBE goal.

 

Name of Firms

Work Description

Amount

% of Total Contract

Paid Prior M/WBE Commitment

 

$102,993.53

5.92%

Unpaid Prior M/WBE Commitment

 

$238,484.50

13.70%

1. Aviles Engineering Corporation

Geotechnical Services

$36,111.00

2.07%

2. Aguirre & Fields, L.P.

Structural Services

$35,000.00

2.01%

3. B&E Reprographics, Inc.

Reprographics Services

$4,629.00

0.27%

4. Gupta & Associates, Inc.

Electrical/SCADA

$123,000.00

7.07%

5. SP Engineering, Inc.

Traffic Control Plans

$24,074.00

1.38%

 

 

$564,292.03

32.42%

 

  

FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

 

____________________________________

Carol Ellinger Haddock, P.E.

Director

Houston Public Works

 

WBS No. R-000267-0126-3

Prior Council Action:

Ordinance 2014-0385, dated April 30, 2014


Amount and Source of Funding:

$343,200.00 from Fund No. 8500 - Water and Sewer System Consolidated Construction Fund.

 

Original (previous) appropriation of $1,658,900.00 from Fund No. 8500 – Water and Sewer System Consolidated Construction Fund.   


Contact Information:

R. Jeff Masek, P.E. CCM

Acting Senior Assistant Director, Capital Projects