20TY38 Contract Award / Alsay Incorporated

Agenda Item#: 45.


 
                               
Summary:

ORDINANCE appropriating $2,897,600.00 out of Water & Sewer System Consolidated Construction Fund, awarding contract to ALSAY INCORPORATED for Rehabilitation of existing Water Wells Various Sites; setting a deadline for the bidder's execution of the contract and delivery of all bonds, insurance, and other required contract documents to the City; holding the bidder in default if it fails to meet the deadlines; providing funding for CIP Cost Recovery, construction management, and contingencies related to construction of facilities financed by the Water & Sewer System Consolidated Construction Fund - DISTRICTS A - STARDIG; F - LE; G - TRAVIS; J - LASTER and K - GREEN

TAGGED BY COUNCIL MEMBER CHRISTIE

This was item 28 on Agenda of January 3, 2018

Background:

SUBJECT: Contract Award for Rehabilitation of Existing Water Wells Various Sites.

 

RECOMMENDATION: (SUMMARY) Accept low bid, award Construction Contract and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project is part of the City’s program to upgrade and rehabilitate ground water production facilities.  It will meet the area’s water demand and ensure compliance with the Texas Commission on Environmental Quality regulations.

 

DESCRIPTION/SCOPE: This project consists of rehabilitating water wells at various locations. The Contract duration for this project is 420 calendar days. This project was designed by LBG-Guyton Associates.

 

LOCATION: The project includes the following locations as well as other locations:

 

FACILITY

ADDRESS

KEY MAP GRID

COUNCIL DISTRICT

Katy Addicks, Well No. 11

1100-1/2 N. Eldridge

448Y

A

District 54, Well No. 3A

3322 Crossview Drive

490Y

F

District 10, Well No. 1

931 Ivy Wall Drive

488F

G

District 71, Well No. 2

12220 Whittington Drive

489N

G

Southwest, Well No. 9

4410 Westpark Drive

491Z

G

Southwest, Well No. 3SB

5730 Westpark Drive

491X

J

Southwest, Well No. 8

8700 Westpark Drive

530C

J

Ridgemont, Well No. 2

5230 Castlecreek Lane

571Y

K

 

BIDS: This project was advertised for bidding on August 11, 2017. Bids were received on September 21, 2017.  The three (3) bids are as follows:

 

 

Bidder

Bid Amount

1.

Alsay Incorporated

$2,497,743.00

2.

Weisinger Incorporated

$2,770,772.00

3.

Layne Christensen Co.

$2,775,647.00

 

AWARD: It is recommended that this construction contract be awarded to Alsay Incorporated with a low bid of $2,497,743.00 and Addendum Numbers 1 and 2 be made a part of this Contract.

 

PROJECT COST: The total cost of this project is $2,897,600.00 to be appropriated as follows:

 

· Bid Amount

$2,497,743.00

· Contingencies

$124,887.15

· CIP Cost Recovery

$74,969.85

· Construction Management

$200,000.00

 

Construction Management Services will be provided by LBG-Guyton Associates under a previously approved contract.

 

HIRE HOUSTON FIRST: The proposed contract requires compliance with the City’s ‘Hire Houston First’ (HHF) ordinance that promotes economic opportunity for Houston business and supports job creation. In this case Alsay Incorporated is a designated HHF company, but they were the successful awardee without application of the HHF preference.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WSBE PARTICIPATION: The contractor has submitted the following proposed program to satisfy the 8% MBE goal and 3% WBE goal for this project.

 

 

MBE - Name of Firms

Work Description

Amount

% of Contract

1.

Escalante Construction, Inc.

Concrete Construction

$ 199,820.00

8.00%

 

 

TOTAL

$ 199,820.00

8.00%

 

 

WBE - Name of Firms

Work Description

Amount

% of Contract

1.

Macaulay Controls Company

Instrument Supplier

$ 37,466.15

1.50%

 

 

TOTAL

$ 37,466.15

1.50%

 

 

SBE - Name of Firms

Work Description

Amount

% of Contract

1.

Energy Electric Supply Inc.

Pump Supplier

$ 37,466.15

1.50%

 

 

TOTAL

$ 37,466.15

1.50%

 

FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

All known rights-of-way, easements and/or right-of-entry required for the project have been acquired.

 

 

 

____________________________________

Carol Ellinger Haddock, P.E.

Acting Director

Department of Public Works and Engineering

 

WBS No. S-000200-0024-4


Amount and Source of Funding:

$2,897,600.00 from Fund No. 8500 – Water and Sewer System Consolidated Construction Fund


Contact Information:

R. Jeff Masek, P.E., CCM

Acting Senior Assistant Director, Capital Projects

Phone: (832) 395-2387