CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 1/9/2018
District E, District F, District G, District J
Item Creation Date: 10/31/2017

20RJM24 Accept Work / Blastco Texas, Inc.

Agenda Item#: 10.


 
                               
Summary:

RECOMMENDATION from Acting Director Department of Public Works & Engineering for approval of final contract amount of $2,603,658.99 and acceptance of work on contract with BLASTCO TEXAS, INC for Rehabilitation of New Water Storage Tanks at Various Locations - Package 6 - 6.01% under the original contract amount - DISTRICTS E - MARTIN; F - LE; G - TRAVIS and J - LASTER

Background:

SUBJECT: Accept Work for Rehabilitation and New Water Storage Tanks at Various Locations – Package 6.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $2,603,658.99 or 6.01% under the original Contract Amount, accept the Work and authorize final payment.

 

 PROJECT NOTICE/JUSTIFICATION: This project was part of the City’s Water Storage Tank Rehabilitation and Replacement Program and is required to ensure compliance with the Texas Commission on Environmental Quality regulations.

 

 DESCRIPTION/SCOPE: This project consisted of rehabilitation of four ground storage tanks and one elevated storage tank at four pumping stations. Demolition of two ground storage tanks and construction of one new ground storage tank at one pumping station in accordance with technical specifications, project drawings, and contract documents. IDS Engineering Group designed the project with 420 calendar days allowed for construction. The project was awarded to Blastco Texas, Inc. with an original Contract Amount of $2,770,250.00.

 

 LOCATION:  Facility is located at various locations:

 

Water Plant

Address

Key Map

Council District

Kingwood #1 – GST 1 & GST 2

2310 N. Park

296V

E

Forest Cove #2 – GST 1 & GST 3

1110 Mustang Trail

336E

E

District 218 – EST 1

12705 Brantrock

528D

F

District 71 – GST 1

1610 Hayes

489P

G

District 184 – GST 1

10518 Beechnut

529L

J

 

 CONTRACT COMPLETION AND COST: The Contractor, Blastco Texas, Inc. has completed the work under the subject Contract. The project was completed within the established completion date with an additional 117 days approved by Change Order Nos. 2-3. The final cost of the project, including overrun and underrun of estimated unit price quantities and previously approved Change Order Nos. 1-2 is $2,603,658.99 a decrease of $166,591.01 or 6.01% under the original Contract Amount. The decreased cost is a result of the difference between planned and measured quantities.

 

 

 M/WSBE PARTICIPATION: The advertised M/WBE contract goal for this project was 11%. The M/WBE plan established for this project was 11%. According to Office of Business Opportunity, the participation was 18.31%. Contractor’s M/WBE performance evaluation was rated Outstanding.

 

 _________________________________

Carol Ellinger Haddock, P.E.

Acting Director

Department of Public Works and Engineering

 

WBS No. S-000600-0046-4

Prior Council Action:

Ordinance 2015-1297 Dated December 16, 2015


Amount and Source of Funding:

No additional funding required.

 

Original appropriation of $3,182,700.00 from Water and Sewer System Consolidated Construction Fund No. 8500
Contact Information:

R. Jeff Masek, P.E., CCM

Acting Senior Assistant Director, Capital Projects

Phone: (832) 395-2387