CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 12/19/2017
District I, District K
Item Creation Date:

20RJM19 Accept Work / Industrial TX Corp

Agenda Item#: 6.


 
                               
Summary:

RECOMMENDATION from Acting Director Department of Public Works & Engineering, for approval of final contract amount of $2,279,701.07 and acceptance of work on contract with INDUSTRIAL TX CORP. for Lift Station Renewal/Replacement Project: Hunterwood M.U.D. and Northbrook - 3.90% under the original contract amount - DISTRICTS I - GALLEGOS and K - GREEN

Background:

SUBJECT: Accept Work for Lift Station Renewal/Replacement Project: Hunterwood M.U.D. (FN 482), and Northbrook.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $2,279,701.07 or 3.90% under the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the City’s ongoing program to upgrade its wastewater lift station facilities.

 

DESCRIPTION/SCOPE: This project consisted of rehabilitation of the Hunterwood M.U.D. and Northbrook Lift Stations.  ARCADIS U.S., Inc. designed the project with 332 calendar days allowed for construction. The project was awarded to Industrial TX Corp. with an original Contract Amount of $2,372,295.00.

 

LOCATION: The project areas are located as follows:

 

Description

Address

Key Map Grid

Council District

Hunterwood M.U.D. Lift Station Rehabilitation

6230 S. Lake Houston Parkway

456R

I

Northbrook Lift Station Rehabilitation

12414 ½ Garden Street

570F

K

 

CONTRACT COMPLETION AND COST: The Contractor, Industrial TX Corp. has completed the work under the subject Contract. The project was completed on time with an additional 112 days approved by Change Order No. 1. The final cost of the project, including overrun and underrun of estimated unit price quantities is $2,279,701.07, a decrease of $92,593.93 or 3.90% under the original Contract Amount. The decreased cost is a result of the difference between planned and measured quantities.

M/WSBE PARTICIPATION: The advertised MWBE Contract goal for this project was 18%. The M/WSBE plan established for this project was 26.26%. According to the Office of Business Opportunity, the participation was 35.98%. The Contractor’s M/WBE performance evaluation was rated satisfactory due to failure to utilize one of the originally listed subs or request a deviation as required.

 

 

  

____________________________________

Carol Ellinger Haddock, P.E.

Acting Director

Department of Public Works and Engineering

 

WBS No. R-000267-111A-4

Prior Council Action:

Ordinance 2015-0176 Dated February 25, 2015

Amount and Source of Funding:

No additional funding required.

 

Original appropriation of $2,682,000.00 from Fund No. 8500 - Water and Sewer System Consolidated Construction.

 

 

 


Contact Information:

R. Jeff Masek, P.E., CCM

Acting Senior Assistant Director, Capital Projects

Phone: (832) 395-2387