Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 12/19/2017
District A, District E, District F, District G
Item Creation Date: 10/27/2017

20RJM18 Accept Work / Blastco Texas, Inc.

Agenda Item#: 5.


 
                               
Summary:

RECOMMENDATION from Acting Director Department of Public Works & Engineering, for approval of final contract amount of $3,272,538.34 and acceprance of work on contract with BLASTCO TEXAS, INC for Rehabilitation and New Water Storage Tanks at Various Locations - Package 4 - 6.78% under the original contract amount - DISTRICTS A - STARDIG; E - MARTIN; F - LE and G - TRAVIS

Background:

SUBJECT: Accept Work for Rehabilitation and New Water Storage Tanks at Various Locations – Package 4.

 

RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $3,272,538.34, or 6.78% under the original Contract Amount, accept the Work and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: This project was part of the City’s Water Storage Tank Rehabilitation and Replacement Program and is required to meet with Texas Commission on Environmental Quality regulations.

 

DESCRIPTION/SCOPE: This project consisted of rehabilitation of three ground storage tanks, three hydro-pneumatic tanks, and one elevated storage tank at five pumping stations, demolition and construction of one ground storage tank at one pumping station and new construction of one ground storage tank at one pumping station in accordance with the technical specifications, project drawings and contract documents. IDS Engineering Group designed the project with 420 calendar days allowed for construction. The project was awarded to Blastco Texas, Inc. with an original Contract Amount of $3,510,472.00.

 

LOCATION: The project sites are as follows:

SITE LOCATIONS

ADDRESS

KEY MAP

COUNCIL DISTRICT

District 237

8755 Mills Road

370J

A

Kingwood # 3

8750 Mills Branch Dr.

297Z

E

Belleau Woods

3422 White Deer Ln.

336Q

E

District 142

1703 West Bay Area

617V

E

Brookfield

9007 Dairy View Ln.

528R

F

Park Glen West

10630 S. Kirkwood

529W

F

District 175

1206 Arrow Hill.

488F

G

 

CONTRACT COMPLETION AND COST: The Contractor, Blastco Texas, Inc. has completed the work under the subject Contract. The project was completed on time with an additional 53 days approved by Change Order Nos. 1 and 2. The final cost of the project, including overrun and underrun of estimated unit price quantities is $3,272,538.34, a decrease of $237,933.66 or 6.78% under the original Contract Amount, and under 5% contingency amount. The decreased cost is a result of the difference between planned and measured quantities.

 M/WSBE PARTICIPATION: The advertised M/WBE contract goal for this project was 11.00%. The M/WSBE plan established for this project was 15.00%. According to Office of Business Opportunity, the participation was 15.21%.  Contractor’s M/WBE performance evaluation was rated Satisfactory. 

 

 

 

_________________________________

Carol Ellinger Haddock, P.E.

Acting Director

Department of Public Works and Engineering

 

WBS No. S-000600-0044-4

 

 

Prior Council Action:

Ordinance No. 2015-1185, dated December 2, 2015


Amount and Source of Funding:

No additional funding required.

 

Total (original) appropriation of $4,021,800.00 from Water and Sewer System Consolidated Construction Fund No. 8500


Contact Information:

R. Jeff Masek, P.E., CCM

Acting Senior Assistant Director, Capital Projects

Phone: (832) 395-2387


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet
MapsBackup Material