Subject: Purchase of additional 105 Mitigation Stream Credits from SPLENDORA, LLC, a limited liability company, in order to obtain the US Army Corps of Engineers (USACE) 404 Permit required for the 320 million gallons per day expansion of North East Water Purification Plant (NEWPP) Expansion; WBS No. S-000065-0002-3.
Recommendation: Approve an ordinance appropriating funds, and approving the agreement between SPLENDORA, LLC, a limited liability company, and City of Houston; authorizing the payments for the purchase of mitigation credits.
Specific Explanation: This project is required to meet regulatory mandates of the Texas Commission on Environmental Quality and the Harris-Galveston Subsidence District Surface Water Conservation Plan. Under the second supplement (s) between city and authorities, the city will be responsible for approximately 16% of the costs of NEWPP expansion and the Authorities will be responsible for the remainder. It is intended that the NEWPP expansion be completed in two phases. The first phase of 80 million gallons of water per day to be substantially complete no later than August 31, 2021 and the second phase of 240 million gallons of water per day to be substantially complete no later than June 30, 2024 for a total of 320 million gallons of water per day. This project was described and briefed to Transportation, Technology, and Infrastructure Committee on February 13, 2017.
The construction of the NEWPP 320 million gallons per day plant expansion will generate unavoidable impacts to certain jurisdictional streams and wetlands of the United States. As a part of the approval process for the project, the department of Public Works and Engineering is seeking certain approvals from various regulatory agencies, including, without limitation, a permit from the USACE under section 404 of the Clean Water Act (the “404 Permit”). It is anticipated that the 404 Permit will require the City to compensate for the project’s adverse impacts by purchasing sufficient, suitable stream and wetland credits from an operator of a compensatory mitigation bank. A site survey was conducted by SWCA Environmental Consultants, a sub-consultant to Carollo Engineering, the Project Technical Consultant, to determine the extent of impact of this project to existing wetlands. Impacts were identified to several classifications of wetlands, all of which the City will be required to mitigate in accordance with the approved permit.
This request addresses the proposed mitigation related impacts identified in the US Army Corps of Engineer's evaluation necessitating the need to purchase 105 additional stream credits from the Houston-Conroe Mitigation Bank. There are a limited number of Mitigation Bank Credits available, and they are offered on a first come, first served basis. This purchase is necessary to meet the requirements of the final 404 permit to be approved by the US Army Corps of Engineers. Failure to obtain required mitigation bank credits could jeopardize the permitting process and delay the completion of the NEWPP Expansion. A final decision by the US Army Corps of Engineers on 404 permit application is expected by December 2017. These credits are being purchased in accordance with US Army Corps of Engineers Permit application for impacts made at the Northeast Water Purification Plant, and this is the only location approved by the US Army Corps of Engineers, by our permit, for mitigation of these impacts. The Sole Source Purchase of Wetlands and Stream Bank Mitigation Bank Credits is enclosed.
This will be the fourth of a series of mitigation credit purchases. Once the US Army Corps of Engineers makes a decision to approve the 404 Permit, we may receive the option to purchase mitigation credits from the other mitigation banks and additional appropriations may be needed.
The total cost to purchase the stream mitigation credits is $22,575.00 and to be appropriated as follows:
• The City of Houston will contribute $3,612.00.
• The Water Authorities will contribute $18,963.00.
PREVIOUS HISTORY:
On May 31, 2017, City Council approved the purchase of stream mitigation credits from Forestar (USA) Real Estate Group Inc., under Ordinance No. 2017-392 appropriating $599,850.00.
On September 13, 2017, City Council approved the purchase of wetland mitigation credits from Gin City Restoration, LLC and Mitigation Solutions USA, LLC under Ordinance No. 2017-693 appropriating $4,036,500.
ESTIMATED FISCAL OPERATING IMPACT:
No significant Fiscal Operating impact is anticipated as a result of this project.
______________________________
Carol Ellinger Haddock, P.E.
Acting Director
Department of Public Works and Engineering