SUBJECT: Accept Work for Sanitary Sewer Rehabilitation by Sliplining and Pipe Bursting Methods.
RECOMMENDATION: (Summary) Pass a motion to approve the final contract amount of
$3,884,587.16, which is 4.08% under the original contract amount, accept the work, and authorize final payment.
PROJECT NOTICE/JUSTIFICATION: Under this project, the contractor provided sanitary sewer rehabilitation by sliplining and pipe bursting methods to deteriorated sewer collection systems throughout the City.
DESCRIPTION/SCOPE: This project consisted of sanitary sewer rehabilitation by sliplining and pipe bursting methods. The project was awarded to PM Construction & Rehab, LLC with an original contract amount of $4,049,950.13. The Notice to Proceed date was 07/10/2013 and the project had 540 calendar days for completion.
LOCATION: This work order project was located at various locations within Council Districts A, B and H.
CONTRACT COMPLETION AND COST: The contractor, PM Construction & Rehab, LLC, has completed the work under the contract. The contract was completed within the contract time. The final cost of the project is $3,884,587.16, a decrease of $165,362.97 or 4.08% under the original contract amount. Less pipe bursting was needed than anticipated.
The final amount of this work order contract was not affected by Change Orders No. 1, No. 2 and No. 3.
MWDBE PARTICIPATION: The MWDBE goal for this project was 21.66%. According to the Office of Business Opportunity, the actual participation was 22.35%. The contractor was awarded an “Outstanding” rating from the Office of Business Opportunity.
Carol Ellinger Haddock, P.E.
Acting Director
Department of Public Works and Engineering
WBS# R-000266-0201-4