RECOMMENDATION from Acting Director Department of Public Works & Engineering, for approval of final contract amount of $4,167,335.40 and acceptance of work on contract with MCKINNEY CONSTRUCTION, INC, for Water Line Replacement in Sherwood Forest Area - 4.22% under the original contract amount - Enterprise Fund - DISTRICT G - TRAVIS |
| | | | | | | | Background:
SUBJECT: Accept Work for Water Line in Sherwood Forest Area. WBS No. S-000035-0184-4.
RECOMMENDATION: (SUMMARY) Pass a motion to approve the final Contract Amount of $4,167,335.40 or 4.22% under the original Contract Amount, accept the Work and authorize final payment.
PROJECT NOTICE/JUSTIFICATION: This project was part of the City’s Water Line Replacement Program. This program was required to replace and upgrade water lines within the City to increase availability of water, improve circulation and fire protection.
DESCRIPTION/SCOPE: This project consisted of the construction of approximately 33,000 linear feet of water lines with related appurtenances in the Sherwood Forest Area. Jones & Carter, Inc. designed the project with 305 calendar days allowed for construction. The project was awarded to McKinney Construction, Inc. with an original Contract Amount of $4,350,750.00.
LOCATION:
|
Area
|
Bounded By
|
Key Map Grid
|
Council District
|
|
1
|
I-10 on the north, Memorial Woods Drive and Memorial Drive on the south, North Post Oak Road on the east and Memorial Woods Circle, Chatsworth and Pinehaven Drive on the west
|
491 C, D, E, F, G, H, L & M
|
G
|
|
2
|
Chatsworth Drive on the north, Buffalo Bayou on the south, Pinehaven Drive and Memorial Drive on the east and Friar Tuck Lane and Buckingham Drive on the west
|
491 C, D, E, F, G, H, L & M
|
G
|
|
3
|
Memorial Drive and Briar Branch Bayou on the north, Pineland Drive and HCFCD Unit 100-00-00 on the south, Westminister Drive on the east and Lindenwood Drive on the west
|
491 C, D, E, F, G, H, L & M
|
G
|
|
4
|
HCFCD Unit W100-00-00 on the north, Woodway Drive on the south, HCFCD Unit W100-00-00 on the east and Sage Road on the west
|
491 C, D, E, F, G, H, L & M
|
G
|
CONTRACT COMPLETION AND COST: The Contractor, McKinney Construction Inc., has completed the work under the subject Contract. The project was completed beyond the established completion date. Liquidated damages in the amount of $20,800.00 for 26 days at $800/day were assessed and reflected in the final payment to the Contractor. The final cost of the project, including overruns and underruns of estimated unit price quantities and previously approved Change Order Nos. 1 and 2 is $4,167,335.40, a decrease of $183,414.60 or 4.22% under the original Contract Amount. The decreased cost is a result of the difference between planned and measured quantities.
This decrease is primarily the result of an underrun in Extra Unit price Items and certain other items not used, which was not necessary to complete the project.
M/WSBE PARTICIPATION: The M/WBE goal established for this project was 21.72%. According to Office of Business Opportunity, their participation was 33.98%. Contractor’s M/WBE performance evaluation was outstanding.
_________________________________
Carol Ellinger Haddock, PE
Acting Director
Department of Public Works and Engineering
WBS No. S-000035-0184-4
|
| | | | | | | | Prior Council Action:
Ordinance 2015-0378, dated 04/29/2015
|
| | | | | | | | Amount of Funding:
Total (original) appropriation of $5,058,900.00 from Water and Sewer System Consolidated Construction Fund No. 8500. This project is eligible for low interest funding through a State Revolving Fund (SRF) Equivalency loan.
|