Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 8/1/2017
ALL
Item Creation Date: 4/13/2017

20JAI686 PES / V&A Consulting Engineers, Inc.

Agenda Item#: 33.


 
                               
Summary:

ORDINANCE appropriating $250,000.00 out of Water & Sewer System Consolidated Construction Fund and approving and authorizing Professional Engineering Services Contract between the City of Houston and V&A CONSULTING ENGINEERS, INC for Work Order Engineering Services for Wastewater Odor Control; providing funding for construction of facilities financed by the Water & Sewer System Consolidated Construction Fund

Background:

SUBJECT: Professional Engineering Services Contract between the City and V&A Consulting Engineers, Inc. for Work Order Engineering Services for Wastewater Odor Control. WBS No. R-000020-0056-3

RECOMMENDATION: (SUMMARY)
An ordinance approving a Professional Engineering Services Contract with V&A Consulting Engineers, Inc. and appropriate funds.

PROJECT NOTICE/JUSTIFICATION: This project is part of the City’s ongoing program to provide professional engineering services for the improvement to the Odor Control Systems for various wastewater facilities.

DESCRIPTION/SCOPE: This project consist of preparation of the complete design packages for the various Sanitary Sewer Odor Control System improvements located throughout the City, based on individual “Work Order” issued by the Department of Public Works and Engineering, Public Utilities Division.

LOCATION: This Project area is generally bounded by the City Limits.

SCOPE OF CONTRACT AND FEE:
Under the scope of the professional engineering services contract, the consultant will perform work on any Sanitary Sewer Odor Control System which may require an accelerated response in preparation of plans, specifications, and bid documents. This project(s) will be initiated through a work order process that will include specific and well-defined scope of work.

The total cost of this project is $250,000.00 to be appropriated as follows: $250,000.00 for Contract services.

PAY OR PLAY PROGRAM:
The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

M/WBE PARTICIPATION:
V&A Consulting Engineers, Inc is committed to achieving the 24% M/WBE overall goal set for this contract. The following M/WBE firms will provide services for this project. Due to the work order nature of this project, specific distribution between MWBE firms will be dependent upon the scope of work for the tasks issued by the City.

 

     Name of Firms

Work Description

 1. Fivengineering, LLC, DBA 5engineering

Engineering Services

 2. Gupta & Associates, Inc. 

Electrical Engineering Services

 3. Amani Engineering, Inc. 

Surveying Services

 

ESTIMATED FISCAL OPERATING IMPACT:
No significant Fiscal Operating impact is anticipated as a result of this project.



___________________________
Karun Sreerama, MBA, PhD, PE
Director
Department of Public Works and Engineering


WBS No. R-000020-0056-3


Prior Council Action:
N/A
Amount of Funding:
$250,000.00 Water and Sewer System Consolidated Construction Fund No. 8500
Contact Information:

Jason Iken, P.E.

Senior Assistant Director, Wastewater Operations Branch

Phone: (832)395-4989


ATTACHMENTS:
DescriptionType
Signed CoversheetSigned Cover sheet