ORDINANCE appropriating $1,155,378.22 out of Street and Traffic Control and Storm Drainage DDSRF; approving and authorizing first amendment to Professional Engineering Services Contract between City of Houston and CONSOR ENGINEERS, LLC for Neighborhood Street Reconstruction (NSR) Project 454 (Approved by Ordinance No. 2013-0371); providing funding for CIP Cost Recovery relating to construction of facilities financed by the Street and Traffic Control and Storm Drainage DDSRF - DISTRICT G - HUFFMAN

Background:

SUBJECT: Amendment to the Professional Engineering Services Contract between the City and Consor Engineers, LLC, formerly AIA Engineers, LTD for Neighborhood Street Reconstruction (NSR) Project 454.

 

RECOMMENDATION: Approve the Amendment to the Professional Engineering Services Contract with Consor Engineers, LLC, formerly AIA Engineers, LTD and appropriate funds.

 

PROJECT NOTICE/JUSTIFICATION: This project will replace existing residential streets that have been deteriorated beyond economical repair and normal maintenance and improve drainage.

 

DESCRIPTION/SCOPE: Project provides design of the storm drainage including roadway concrete paving, curbs, sidewalks, driveways, street lighting and necessary underground utilities. This project has been identified as Subproject One under NSR Project 454.

 

LOCATION:

 

STREET NAME

LOCATION

COUNCIL DISTRICT

Bordley Drive

Chimney Rock Road to Rocky River Road

G

Cedar Creek Drive

Chimney Rock Road to Fieldwood Drive

G

Doliver Drive

Chimney Rock Road to Rocky River Road

G

Longmont Drive

Chimney Rock Road to Rocky River Road

G

Lynbrook Drive

Chimney Rock Road to Rocky River Road

G

Tilbury Drive

Sherbrooke Road to Rocky River Road

G

Fieldwood Drive

Cul-De-Sac to South Post Oak Lane

G

Huckleberry Lane

San Felipe St to Sage Rd

G

Tangle Lane

Sage Road to South Post Oak Lane

G

Sherbrooke Road

Lynbrook Road to San Felipe Street

G

York Town Road

Cedar Creek Drive to San Felipe Street

G

 

 

PREVIOUS HISTORY AND SCOPE: City Council approved the original contract on May 1, 2013 under Ordinance No. 2013-0371. The scope of services under the original contract consisted of Phase I – preliminary design, Phase II – final design, and Phase III – construction phase services and additional services. Under this contract, the Consultant has accomplished Phase I – preliminary design, and 65 % Phase II – final design. The below subsequent Council Actions associated with this contract include:

 

Ord. No.

Ord. Date

Type

Scope of the Action

 Accomplished to Date

2016-0436

06-08-2016

Add

Completion of the remaining Basic Phase II and Phase III and Additional Services

Phase I, II, and III of subproject 1 and Phase I of subproject 1A.

 

 SCOPE OF THIS AMENDMENT AND FEE: Under the scope of this amendment, the contract will be updated to incorporate the latest version of Exhibit C - Raw Salaries. A fee of $754,062.00 is budgeted for Basic Services and $346,298.22 for Additional Services.

 

The total requested appropriation is $1,155,378.22 to be appropriated as follows: $1,100,360.22 for contract services and $55,018.00 for CIP Cost Recovery.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s ‘Pay or Play’ ordinance regarding health benefits for employees of City Contractors. In this case, the Contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATION: The M/WBE goal established for this project is 24.00%. The original contract amount and subsequent appropriations total $1,664,518.71. The Consultant has been paid $1,664,500.00 (100.00%). Of this amount, $360,829.00 (21.68%) has been paid to M/WBE sub-contractors to date. Assuming approval of the requested additional appropriation, the contract amount will increase to $2,764,878.93. The Consultant proposes the following plan to meet the M/WBE goal.

 

 

Name of Firms

Work Description

Amount

% of Total Contract

Paid Prior M/WBE Commitment

 

$360,829.00

13.05%

1. Progressive Consulting Engineers, PLLC, dba Progressive Traffic & Transportation

Civil engineering services

$  79,782.00

 2.89%

2. Geotest Engineering, Inc.

Construction management, residential remodeling

$106,717.00

3.86%

3. Kuo & Associates, Inc.

Surveying and mapping services

$117,127.50

         4.24%

4. Disha Services

Engineering services

$  77,040.00

 2.79%

 

 

 

 

 

TOTAL

$741,495.50

26.81%

 

 

FISCAL NOTE: No significant Fiscal Operating impact is anticipated as a result of this project.

 

 

 

 

_________________________________

Randall V. Macchi, JD

Director, Houston Public Works

 

WBS No. N-000386-0001-3

 

Prior Council Action:

Ordinance No. 2013-0371, dated 05-01-2013

Ordinance No. 2016-0436, dated 06-08-2016

Amount and Source of Funding:

Total $1,155,378.22 from Fund No. 4042 - Dedicated Drainage and Street Renewal Capital Fund – Drainage Charge

 

Original appropriation of $1,177,100.00 from Fund No. 4042 – Street & Traffic Control and Storm Drainage DDSRF.

Subsequent appropriation of $750,000.00 from Fund No. 4042 - Street & Traffic Control and Storm Drainage DDSRF.

Contact Information:

Name

Service Line

Contact No.

Roberto Medina, Assistant Director

DO-HPW Council Liaison Office

832.395.2456

Maria Perez, HPW Agenda Coordinator

DO-HPW Council Liaison Office

832.395.2282

Tanu Hiremath, P.E., CFM, ENV SP Assistant Director

HPW - Engineering

832-395-2291


ATTACHMENTS:
DescriptionType
Signed coversheetSigned Cover sheet
MapsBackup Material