20JAI641 Accept Work/Envirowaste

Agenda Item#: 4.


 
                               
Summary:

RECOMMENDATION from Director of Public Works & Engineering for approval of final contract amount of $595,796.47 and acceptance of work on contract with ENVIROWASTE SERVICES GROUP, INC for Sanitary Sewer Cleaning and Television Inspection In Support of Rehabilitation  2.23% under the original contract amount (4277-63) - DISTRICTS A - STARDIG; B - DAVIS; C - COHEN; D - BOYKINS; E - MARTIN; F - LE; H - CISNEROS; I - GALLEGOS and K - GREEN

Background:

SUBJECT:  Accept Work for Sanitary Sewer Cleaning and Television Inspection In Support of Rehabilitation, WBS# R-000266-0173-4.

 

RECOMMENDATION:  (Summary)  Pass a motion to approve the final contract amount of $595,796.47, which is 2.23% under the original contract amount, accept the work, and authorize final payment.

 

PROJECT NOTICE/JUSTIFICATION: Under this project, the contractor provided sanitary sewer cleaning and television inspection in support of rehabilitation to deteriorated sewer collection systems throughout the City.

 

DESCRIPTION/SCOPE: This project consisted of sanitary sewer cleaning and television inspection in support of rehabilitation. The project was awarded to Envirowaste Services Group, Inc. with an original contract amount of $609,362.49. The Notice to Proceed date was 03/29/2012 and the project had 730 calendar days for completion.

 

LOCATION:  This work order project was located at various locations within Council Districts A, B, C, D, E, H, I, J and K.

 

CONTRACT COMPLETION AND COST:  The contractor, Envirowaste Services Group, Inc., has completed the work under the contract.  The contract was completed within the contract time with an additional 120 days approved by Change Order No. 1. The final cost of the project is $595,796.47, a decrease of $13,566.02 or 2.23% under the original contract amount. Less cleaning was needed than anticipated.

 

The final amount of this work order contract was not affected by Change Order No. 1.

 

MWDBE PARTICIPATION:  No City M/WBE participation goal was established for this project as the contract amount did not exceed the threshold of $1,000,000.00 required for a goal oriented contract per Section 15-82 of the Code of Ordinances.

Prior Council Action:
Ordinance 2011-1196, dated 12/21/2011
Amount of Funding:

No additional funding required.

 

Original appropriation of $644,831.00 for construction and contingencies from Water and Sewer System Consolidated Construction Fund No. 8500.

Contact Information:

Jason Iken, P.E.

Senior Assistant Director

Phone:  (832) 395-4989