Item Coversheet

CITY OF HOUSTON - CITY COUNCIL

Meeting Date: 6/14/2016
ALL
Item Creation Date: 5/27/2016

20PJ19 Add'l Approp - Weston Solutions

Agenda Item#: 25.


 
                               
Summary:

ORDINANCE appropriating $165,000.00 out of Water & Sewer System Consolidated Construction Fund as an additional appropriation to the Construction Management and Inspection Services Agreement between the City of Houston and WESTON SOLUTIONS, INC associated with contract award for Sewer Service to Unserved Areas Package 1: Shared Facilities (Regional) Sanitary Sewer Improvements - Magnolia Point Lift Station, Force Main & Trunk Main; Strange’s Camp Lift Station & Force Main (Approved by Ordinance No. 2011-0411, as amended)

Background:

SUBJECT: Additional Appropriation for Construction Management and Inspection Services Contract between the City of Houston and Weston Solutions, Inc. associated with a Contract Award for Sewer Service to Unserved Areas Package 1: Shared Facilities (Regional) Sanitary Sewer Improvements – Magnolia Point Lift Station, Force Main & Trunk Main; Strange’s Camp Lift Station & Force Main; WBS No. R-000801-0013-4.

 

RECOMMENDATION:  (Summary) Approve an ordinance appropriating additional funds to the Construction Management and Inspection Services Contract with Weston Solutions, Inc.

 

PROJECT NOTICE/JUSTIFICATION: These projects are associated with the City’s program to provide sanitary sewer to the Unserved area within the City limit. 

 

DESCRIPTION/SCOPE: This Contract provides for Construction Management and Inspection Services for Construction Branch of the Department of Public Works and Engineering in connection with sanitary sewer service to Unserved Areas Package 1: Shared Facilities (Regional) Sanitary Sewer Improvements – Magnolia Point Lift Station, Force Main & Trunk Main; Strange’s Camp Lift Station & Force Main projects.

 

LOCATION: The projects are located throughout the City of Houston

 

PREVIOUS HISTORY AND SCOPE:  The Construction Branch has issued three (3) work authorizations under this contract. The work authorizations are listed below:

 

W.A. NO.  PROJECT ORDINANCE NO. APPROPRIATED AUTHORIZED
1 Northside Sewer Relief Tunnel Rehabilitation Area 4 2012-0582 $695,000.00 $661,518.00
2 Amy Ridge and Hiram Clarke Lift Station Diversion 2013-0422 $330,000.00 $329,260.80
3 Northside Sewer Relief Tunnel Rehabilitation Area 5 2014-0644 $785.000.00 $604,702.00

 

SCOPE OF THIS SUPPLEMENT AND FEE:  The City Council approved the original Construction Management and Inspection Services Contract on June 1, 2011 under Ordinance Number 2011-0411 with Weston Solutions, Inc. and appropriated $12,000.00 for limited pre-construction review.  This Contract was referenced in Ordinance No. 2013-0422 to perform Construction Management and Inspection services for the Amy Ridge and Hiram Clarke Lift Station Diversion.  The construction contractor exceeded the time to complete the project by more than 50 percent of the original contract time.  Under this Contract, the consultant required additional funds to continue performing Construction Management and Inspection services.  The increased funds are due to the construction contractor, BRH-Garver Construction, L.P. failure to complete the project within the contract time.  The requested appropriation will complete the Construction Management and Inspection services for the proposed Amy Ridge and Hiram Clarke Lift Station Diversion.  The total appropriation is $165,000.00 to be appropriated for contract services.

 

PAY OR PLAY PROGRAM: The proposed contract requires compliance with the City’s “Pay or Play” ordinance regarding health benefits for employees of City contractors. In this case, the contractor provides health benefits to eligible employees in compliance with City policy.

 

M/WBE PARTICIPATION: The M/WBE goal established for this contract is 24%.  The current total authorization for this contract is $1,595,480.80.  The consultant has been paid $1,151,258.16 (72.16%) to date.  Of this amount, $330,627.93 (28.72%) has been paid to M/WBE sub-consultants to date.  

 

 

Prior Council Action:

Ordinance 2011-0411, dated: 06/01/2011

Ordinance 2012-0582, dated: 06/20/2012

Ordinance 2013-0422, dated: 05/08/2013

Ordinance 2014-0644, dated: 06/18/2014

Amount of Funding:

$165,000.00

Water and Sewer System Consolidated Construction Fund No. 8500. 

 

Previous Original Appropriation of $1,822,000.00 from the Water and Sewer System Consolidated Construction Fund No. 8500

Contact Information:

Joseph T. Myers, P.E.

Senior Assistant Director

Phone: (832) 395-2355
ATTACHMENTS:
DescriptionType
Signed RCASigned Cover sheet